IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following is NOT a valid WBS creation approach:
  1. Parametric approach
  2. Top-down approach
  3. Use of organizational guidelines
  4. Use of WBS templates






Q2. Mary is currently drafting a stakeholder engagement plan for her new website development project. Her organization has strict communication guidelines. Mary wants to ensure that her stakeholder engagement strategy aligns with the organizational communications guidelines. Where can she find these guidelines?

  1. Corporate knowledge base
  2. Stakeholder register
  3. Project contract
  4. Lessons learned library
Correct Answer

Q3. Which of the following is TRUE of inspections?

  1. They may not be conducted by the project team.
  2. They test future desires of prospective customers.
  3. They can only be conducted on the final product.
  4. They prevent defective deliverables from reaching the customer.
Correct Answer

Q4. If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity?

  1. 1
  2. 1.3
  3. 6
  4. 3
Correct Answer

Q5. All the monitoring and controlling processes and many of the executing processes can produce change requests as an output. Change requests may require corrective actions and preventive actions. Which of the following are normally affected by corrective and preventive actions?

  1. Defect repair
  2. Regressive baselines
  3. The project baselines
  4. The performance against baselines
Correct Answer

Q6. By policy, the project management office regularly evaluates project performance. This is done in order to ensure standards are being followed. This is an example of:

  1. Plan Quality
  2. Manage Quality
  3. Control Quality
  4. Quality Management
Correct Answer

Q7. You are collecting requirements for your project. For a few requirements you are having difficulty reaching a consensus, so you decide to vote and select the choice which has the largest number of votes. What voting technique is this?

  1. Minority
  2. Unanimity
  3. Majority
  4. Plurality
Correct Answer

Q8. Clear criteria for rewards and a planned system for their use promotes and reinforces desired behaviors in the project. Creating a recognition plan with established times for rewards ensures that recognition takes place and is not forgotten. This is usually part of the:

  1. Project Dashboard
  2. Resource Management Plan
  3. Company HR plan
  4. Communications Management Plan
Correct Answer

Q9. Most project management software packages use a method of constructing a project schedule network diagram known as:

  1. Waterfall Method
  2. Precedence Diagramming Method
  3. Agile Method
  4. Just-in-time Method
Correct Answer

Q10. The most detailed level of the WBS is the _______________ .

  1. Control Account
  2. Work package
  3. Scope statement
  4. Accepted Deliverable
Correct Answer










User Agreement| |Privacy Policy