Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You are working in a matrix project environment where functional managers have control over the resources. You are well aware that not acquiring the project team soon enough for your project could result in changes to the schedule, cost, and quality. To acquire the project team from functional managers, the best technique for you to use is:
  1. Pre-assignment
  2. Virtual teams
  3. Negotiations
  4. Acquisition






Q2. You are working in Lab-X, a laboratory experimental project to research the effect of a virus on human male bodies. This project needs local government approval for carrying out tests on living people. However, the local authorities informed you were informed it would take at least three weeks to obtain authorization for such approval because of the documents involved in the review and approval process. You consider this a risk to the project and would like to send the paperwork in advance to reduce the approval time to one week. Which of the following describes the risk response techniques being employed in this scenario?

  1. Risk mitigation
  2. Risk transfer
  3. Risk accept
  4. Risk avoid
Correct Answer

Q3. As the project manager, you are about to start the define scope process. You have the project charter and the organizational process assets list. Because there are no change requests in your project at this point, what must you have before you begin?

  1. Product analysis
  2. Requirements documentation
  3. Updates to project documents
  4. WBS
Correct Answer

Q4. Testing the entire population:

  1. Take too long.
  2. Provide more information than wanted.
  3. Be mutually exclusive.
  4. Show many defects.
Correct Answer

Q5. The most detailed level of the WBS is the _______________ .

  1. Control Account
  2. Work package
  3. Scope statement
  4. Accepted Deliverable
Correct Answer

Q6. A project manager is trying to budget time for the various processes in the Project Schedule Management Knowledge Area. As project activities are performed, in which of these processes will the majority of effort occur?

  1. Control Schedule
  2. Estimate Activity Durations
  3. Define Activities
  4. Develop Schedule
Correct Answer

Q7. You are a non-technical project manager. Two highly skilled and knowledgeable resources on your project are in conflict over the best technical solution to meet a project requirement. However, this is not affecting the project schedule. Who is initially responsible for the conflict resolution?

  1. The project sponsor is initially responsible for the conflict resolution.
  2. The project manager is initially responsible for the conflict resolution.
  3. Both team members are initially responsible for the conflict resolution.
  4. Either of the team members is responsible for the conflict resolution.
Correct Answer

Q8. Which of the following interpersonal skills is of prime importance during the collection and analysis of stakeholders’ needs and expectations?

  1. Trust building
  2. Conflict resolution
  3. Overcoming resistance
  4. Active listening
Correct Answer

Q9. As project manager, you are unable to allocate as much time to interact with your stakeholders as you would like. Which of the following stakeholders will you make it a priority to get to know?

  1. The stakeholder who is an expert on the product of the project, but is not interested in implementing it in his department.
  2. The manager of the department that will use the product of the project. She is known to be resistant to change.
  3. The project sponsor, with whom you have successfully worked on many projects.
  4. The department employee who is unfamiliar with the product of the project, but open to the positive impacts he believes the product will have on his work environment.
Correct Answer

Q10. A project manager needs to determine if the manufacturing process planned for the new micro-satellites will meet quality standards. Each satellite takes about three days to manufacture and costs US $125,000. The satellites are so small that inspection would destroy them. Under these circumstances, what should the project manager do?

  1. Outsource the inspection to another company with more expertise.
  2. Evaluate the attributes of the population.
  3. Inspect a sample of the satellites.
  4. Decrease the cost of quality.
Correct Answer