Question:

The level of detail of performance reports is described in the:
  1. Project charter.
  2. Communications management plan.
  3. Monthly requests for information by management.
  4. Project’s monthly needs.






Q2. You are about to take over a project from another project manager and find out the following information about the project. Activity Z has an early start (ES) of day 15 and a late start (LS) of day 20. Activity Z is a difficult activity. Cost performance index (CPI) is 1.1; schedule performance index (SPI) is 0.8. There are 11 stakeholders on the project. Based on this information, which of the following would you be the MOST concerned about?

  1. Schedule
  2. Float
  3. Cost
  4. The number of available resources.
Correct Answer

Q3. The business case to justify a project typically contains:

  1. The project's BAC and ETC
  2. Identification of alternatives
  3. Project WBS
  4. Variance Analysis
Correct Answer

Q4. If your project will require redesign after completion of testing, which of the following diagramming techniques would be BEST to use?

  1. GERT
  2. PERT
  3. CPM
  4. ADM
Correct Answer

Q5. The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with all the stakeholders to find out why there were changes and to discover any more. The project work has quieted down when a team member casually mentions to the project manager that he added functionality to a product of the project. Do not worry he says, “I did not impact time, cost, or quality!”

  1. Ask the team member how the need for functionality was determined
  2. Hold a meeting to review the team member’s completed work
  3. Look for other added functionality.
  4. Ask the team member how he knows there is no time, cost, or quality impact.
Correct Answer

Q6. Based on the chart, how is the project doing?

  1. You are in the trouble because there are three activities with no float
  2. You have a lot of flexibility because you have activities with float
  3. You do not have enough information to make a decision
  4. Everything is fine because you have an even number of activities with and without float.
Correct Answer

Q7. You are just starting on a project as project manager. The project sponsor asks you for weekly status updates by email and monthly project status meetings to review the project’s progress. These requirements are documented in the:

  1. Scope statement
  2. Communications management plan
  3. Project charter
  4. Organizational plan
Correct Answer

Q8. A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change?

  1. Inform the customer
  2. Make sure marketing is aware of the change
  3. Understand what functionality was added
  4. Implement change control processes to track the change
Correct Answer

Q9. Which process group corresponds to the “do” part of the plan-do-check-act cycle?

  1. Closing
  2. Monitoring and Controlling
  3. Planning
  4. Executing
Correct Answer

Q10. Management is sending a team of experts for a risk audit. You inform management that you have already completed the risk review process and did not find any shortcomings, so there is no need for a risk audit. However, management is firm on their decision. Which of the following is true about the risk audit and risk review?

  1. A risk audit is performed to see the effectiveness of a risk response plan
  2. A risk audit is performed to see if you are following the correct procedures
  3. A risk review is performed to see if you are following the correct procedures
  4. Both are the same but an audit is done by external experts and a review is done internally
Correct Answer