Question:

You are currently managing an urban development project for a municipal authority. You and your team are managing the project and have outsourced most of the project work to specialist contractors. All the contracts awarded were FFP contracts. The project is almost 50 percent complete, and most of the contractors have requested amendments to their contacts. Work specifications were not clear at the time of contract awards, and as a result, new work requirements have come up. What is your lesson learned?
  1. Never award FFP contracts in the future since they usually result in disputes and contests
  2. Cost-plus contracts are ideal types of contracts for construction projects
  3. Do not award FFP contracts unless the scope of work and specifications are precisely articulated.
  4. Good and credible contractors were not selected for the project at the time of award






Q2. A stakeholder wants to make a change to the work breakdown structure that does NOT affect the time or cost of the project. What is the BEST thing to do?

  1. Tell the stakeholder that this change cannot be made without revising the project management plan.
  2. Make the change.
  3. Meet with management.
  4. Look for other impacts on the project.
Correct Answer

Q3. During a work breakdown structure meeting, you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose the work packages to assist you in estimating, executing, and controlling the project. These decomposed work packages are:

  1. Work packages can't be decomposed into smaller units
  2. Activities
  3. Milestones
  4. Control Accounts
Correct Answer

Q4. Which of the following statements about project teams is incorrect?

  1. The project management team is usually a team external to the project team.
  2. The project management team is a subset of the project team.
  3. For smaller projects, the entire team can share the project management responsibilities.
  4. For smaller projects, the project manager can solely administer project management responsibilities.
Correct Answer

Q5. Which of the following Manage Quality techniques examines problems, constraints, and non-value-added activities that occur during project work?

  1. Sensitivity Analysis
  2. Expected monetary value analysis
  3. Earned Value Analysis
  4. Process Analysis
Correct Answer

Q6. Recommended corrective actions result from which of the following?

  1. Cost aggregation
  2. Bottom-up estimating
  3. Reserve analysis
  4. Control costs.
Correct Answer

Q7. A WBS is BEST described as a tool for tracking:

  1. The schedule.
  2. Resources
  3. Cost
  4. Scope
Correct Answer

Q8. Which of these is not a component of the scope baseline that is contained in the project management plan?

  1. Work Breakdown Structure (WBS)
  2. Requirements documentation
  3. WBS Dictionary
  4. Project Scope Statement
Correct Answer

Q9. You are the project manager of a project whose team has interacted with a number of stakeholders. You believe that in order to have an objective project performance appraisal, you would like to obtain feedback for the project team members from all the people they have worked with, including superiors, peers and subordinates. Project performance appraisals are performed during which of the following processes?

  1. Close Project or Phase
  2. Acquire Resources
  3. Manage Team
  4. Develop Team
Correct Answer

Q10. A large project is underway when one of the team members reviews the project status report. He sees that the project is currently running late. As he looks at the report further, he notices that the delay will cause one of his activities to be scheduled during a time he will be out of the country and cannot work on the activity. This is of great concern because he is very committed to the project being successful and he does not want to be the cause of the project being further delayed. What is the BEST THING for him to do?

  1. Contact the project manager immediately to provide the project manager with his schedule.
  2. Include the information on his next report
  3. Request that the issue be added to the project issue log
  4. Recommend preventive action.
Correct Answer