IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following are ALL outputs of the Perform Integrated Change Control process?
  1. Approved corrective actions, validated defect repair, forecasts, deliverables
  2. Deliverables, implemented corrective actions, rejected change requests, validated defect repair
  3. Approved defect repair, validated defect repair, rejected change requests, approved corrective actions
  4. Recommend corrective actions, validated defect repair, approved defect repair, and rejected change requests.






Q2. Michael and John are having some conflicts and they come to you. Since you are too busy and the problem is complex, you go with the midway of both parties and partially satisfy both of them. What conflict resolution technique are you using here?

  1. Accommodate
  2. Withdraw
  3. Collaborate
  4. Compromise
Correct Answer

Q3. You are an experienced project manager and have managed several data center migration projects. You are currently conducting training on the databases, spreadsheets, and management plans you will use during the lifecycle of the project. This training is a tool and technique in what process?

  1. Manage Team
  2. Acquire Resources
  3. Develop Team
  4. Control Quality
Correct Answer

Q4. A project involved team members situated in Arizona, Nebraska, New York, and Ireland. Which of the following activities becomes crucial in such a team environment?

  1. Team-building
  2. Status reporting
  3. Conflict resolution
  4. Communication planning
Correct Answer

Q5. You are working on a project which is under budget and ahead of schedule. The project is 85% complete, and the client comes and asks you to terminate the project because he fears a possible regulation can impact his project. You review the project parameters and find that you can complete the project before the proposed legislation comes into existence; moreover, you won’t need any extra funding. What will your next steps be?

  1. Tell the client about your findings and ask him to reconsider his decision
  2. Initiate the close project process
  3. Immediately release your team members
  4. Convince your management to discuss the issue with the client
Correct Answer

Q6. How is the three-point estimating related to risk?

  1. It tells you how much assumptions testing is required.
  2. It indicates whether the risk estimate is acceptable.
  3. It indicates the estimate’s degree of uncertainty
  4. It indicates the risk variance
Correct Answer

Q7. The customer starts to have cash flow problems, because other projects are being completed early. The customer notifies the project manager that there will be limits on when funds will be available for the project. The project CPI is currently 1.02, and the estimate to complete is US $927,000. If the project manager performs funding limit reconciliation, there will also MOST likely be a change to the:

  1. Resource assigned.
  2. Number of change requests
  3. Cost baseline
  4. Project schedule 21
Correct Answer

Q8. Which of these is not a component of the scope baseline that is contained in the project management plan?

  1. Work Breakdown Structure (WBS)
  2. Requirements documentation
  3. WBS Dictionary
  4. Project Scope Statement
Correct Answer

Q9. Team members are arguing about the location of specification limits on a control chart. The discussion is becoming heated when the project manager walks in and says: “… It seems that the real problem here is that we do not have enough information about the customer’s specifications. Let’s …”. This is an example of:

  1. Asserting the project manager’s authority.
  2. Problem solving.
  3. Compromising.
  4. Withdrawal.
Correct Answer

Q10. During a team meeting, the team adds a specific area of extra work to the project because they have determined if would benefit the customer. What is wrong in this situation?

  1. The team is gold plating
  2. These efforts shouldn’t be done in meetings
  3. Nothing. This is how to meet or exceed customer expectations.
  4. Nothing. The project manager is in control of the situation.
Correct Answer










User Agreement| |Privacy Policy