IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A project involved team members situated in Arizona, Nebraska, New York, and Ireland. Which of the following activities becomes crucial in such a team environment?
  1. Team-building
  2. Status reporting
  3. Conflict resolution
  4. Communication planning






Q2. The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?

  1. Cost Management
  2. Estimate Costs
  3. Determine Budget
  4. Control Costs
Correct Answer

Q3. Which of the following statements is incorrect?

  1. Developing a project team is the responsibility of the project manager.
  2. A project manager must not acquire resources needed to develop effective project teams.
  3. High team performance can be achieved using open and effective communications.
  4. Teamwork is a critical success factor for a project.
Correct Answer

Q4. Cost of quality includes all costs incurred over the lifetime of the product by investing in the prevention of nonconformance to requirements, appraising the product or service for conformance to requirements, and failing to meet requirements. Which is not an example of the cost of non-conformance?

  1. Rework
  2. Scrap
  3. Liabilities
  4. Destructive testing loss
Correct Answer

Q5. A team member determines that the scope for her activity is no longer valid. She comes to you for advice on making the change. To which of the following documents should the project manager refer to make this change?

  1. The project management information system
  2. The scope management plan
  3. The cost management plan
  4. The work authorization system
Correct Answer

Q6. Sensitivity analysis helps to determine which risks have the most potential impact on the project. A project manager prepared a display chart of sensitivity analysis for his project. The diagram contained a series of bars with the length of the bars corresponding to the risk impact on the project. The longer the bar, the greater was the risk presented. Such a chart is likely to be:

  1. An assessment diagram
  2. A triangular distribution
  3. A tornado diagram
  4. A funnel distribution
Correct Answer

Q7. Jessica is managing an office refurbishment project. All the project stakeholders are identified and classified. The stakeholder engagement plan is also approved. Jessica is managing a project for the first time, and she is relying on the PMBOK guide as a reference to deliver an excellent project. Which of the following processes would provide guidance to Jessica regarding how to execute the approved stakeholder engagement plan?

  1. Monitor Stakeholder Engagement
  2. Manage Stakeholder Engagement
  3. Identify Stakeholders
  4. Plan Stakeholder Engagement
Correct Answer

Q8. Which of the following are the tools and techniques used in both the Plan Communications Management and Manage Communications processes?

  1. Expert judgment
  2. Project reporting
  3. Communication requirements analysis
  4. Communication methods
Correct Answer

Q9. Mary is a project manager for an infrastructure upgrade project in a government agency. She realized recently that a critical scheduled task exceeded its deadline, and the stakeholders are aware of it. The resource manager has permitted Mary to use three more resources to work on and complete the delayed task. Although the three additional resources prove helpful, Mary is still concerned about the task because:

  1. Allocating more resources may result in rework
  2. Allocating more resources may shorten the duration but results in increased risk or cost
  3. Resources may need training to complete the task
  4. Allocating more resources needs stakeholders approval
Correct Answer

Q10. A project manager is meeting with a team member and says, “I know you want to become involved in meetings with the customer. Because of the performance on the project so far, I have rearranged things so you can become involved with the customer.” This is an example of:

  1. Team performance assessment.
  2. Reward power.
  3. Team building
  4. Project performance appraisals.
Correct Answer










User Agreement| |Privacy Policy