Question:

In DMAIC, redesigning of process to either remove bottlenecks or to reduce waste takes place in the ______________ stage.
  1. Define
  2. Measure
  3. Improve
  4. Control






Q2. Factory A produces 100 pieces of wooden legs used in manufacturing tables in 1 hour. The factory in total works for 3 hours. The quality manager decided to check the quality of the output by measuring the length of the legs (in cms). He decides to collect three samples (one for each hour). The sample size for each sample is fixed at 5. The data collected is present in the following table: Leg 1 Leg 2 Leg 3 Leg 4 Leg 5 Sample 1 10.2 10.5 9.8 9.7 10.3 Sample 2 10.4 9.9 10.1 10.2 9.8 Sample 3 9.9 9.8 10.2 10.1 10.4 What is the mean and range of leg length in sample 1?

  1. Mean=10.3;Range=.3
  2. Mean=10.1;Range=.8
  3. Mean=10.2;Range=.6
  4. Mean=9.9;Range=.5
Correct Answer

Q3. When output product of several sources is fed into a common stream, the pattern of the control chart expected is:

  1. Stratification
  2. Trend
  3. Mixture
  4. Cyclic Pattern
Correct Answer

Q4. What must you include when reporting an ANOVA?

  1. Standard deviations, Degrees of freedom, Means, F statistic, P value
  2. Standard deviations, Means, F statistic, P value
  3. Standard deviations, Degrees of freedom, Means, F statistic
  4. Degrees of freedom, F statistic, P value
Correct Answer

Q5. Customers are primarily concerned with ______________

  1. Communication, courtesy, and credibility of the sales person
  2. Competence, courtesy, and security of the sales person
  3. Competence, responsiveness, and reliability of the sales person
  4. Communication, responsiveness, and cleverness of the sales person
Correct Answer

Q6. Given that for the three samples, the value of R bar is .66 and value of d2 corresponding to three is1.128, what is the estimated standard deviation?

  1. .43
  2. .67
  3. .58
  4. .75
Correct Answer

Q7. A bar chart that depicts the frequencies of numerical or measurement data

  1. Sample
  2. Histogram
  3. Check Sheet
  4. Process Map
Correct Answer

Q8. Nonconformance is an expense of:

  1. Profit of quality
  2. Defects of quality
  3. Quality of product
  4. Cost of quality
Correct Answer

Q9. During experimental design, a variable is defined as:

  1. Treatment
  2. Factor
  3. Variance
  4. None of these
Correct Answer

Q10. Attribute charts may be used when:

  1. Several characteristics can be jointly measured
  2. When one particular quality characteristic is of importance
  3. Specific information like process mean is required
  4. None of the above
Correct Answer