IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

During the weekly change control board meeting, you invited the facilities manager to speak about the change request to increase the BTUs of the air conditioning system in the new data center. This is an example of what type of tool and technique in the Perform Integrated Change Control process?
  1. Variance Analysis
  2. Expert Judgment
  3. Project Management Methodology
  4. Project Management Information System






Q2. During the execution of a project, the project manager discovers the project’s stakeholder register is no longer accurate. What should the project manager do?

  1. The project is in execution, the stakeholder register cannot be updated at this stage.
  2. A change request should be issued.
  3. The project is in execution, the Identify Stakeholders process cannot be carried out at this stage.
  4. Review the stakeholder register and carry out the Identify Stakeholders process.
Correct Answer

Q3. You are working on a project to build a canal for irrigation purposes. Six months have passed, and now the team is working as a well-organized unit. Team members are interdependent, working smoothly, and working effectively. What team formation stage is this?

  1. Performing
  2. Storming
  3. Norming
  4. Forming
Correct Answer

Q4. Which of the following is a basic rule or guideline for creating a work breakdown structure?

  1. The first row should describe the products of the project
  2. Each level of a work breakdown structure is a smaller segment of the level above
  3. A work breakdown structure should be like a to-do list, listing in chronological order every activity that needs to be done to complete the project.
  4. A work breakdown structure should be organized by functional areas.
Correct Answer

Q5. A project manager wants to make sure his plans for meeting the training needs of resources, and plans for releasing resources are complete. All of the following are inputs to this activity EXCEPT:

  1. Enterprise environmental factors
  2. Historical information
  3. Project organizational charts
  4. Activity resource requirement.
Correct Answer

Q6. What is the difference between the Monitor and Control Project Work process and the Direct and Manage Project Work process?

  1. The Monitor and Control Project Work and the Direct and Manage Project Work processes are the same.
  2. The Monitor and Control Project Work process monitors the project performance while the Direct and Manage Project Work process is concerned with performing the activities to accomplish project requirements.
  3. The Monitor and Control Project Work process is a sub-process of the Direct and Manage Project Work process.
  4. There is no such thing as the Monitor and Control Project Work process.
Correct Answer

Q7. Which of the following statements correctly define the 100 percent rule for WBS?

  1. The project is only considered complete once all requirements defined in the original scope statements have been completed.
  2. The project is only considered complete once all requirements in the last approved scope baseline have been completed.
  3. The final deliverables should fully conform to product requirements; nothing less, nothing more.
  4. The total of the work at the work package level should roll up to the higher levels so that nothing is left out and no extra work is performed.
Correct Answer

Q8. A project’s financial management reserves are determined in which process:

  1. Estimate Costs
  2. Determine Budget
  3. Control Costs
  4. Estimate Activity Resources
Correct Answer

Q9. Long hours to meet a looming deadline and immense pressure for success from management are causing a decline in team morale. There are occasional conflicts between team members over priorities and resources. How should these non-disruptive conflicts be handled?

  1. Use of disciplinary actions
  2. Using a private, direct, and collaborative approach first
  3. Escalation to senior management
  4. Arbitration
Correct Answer

Q10. It is the middle of the project when the project manager is informed by her scheduler that the project control limits are secure. That same morning she receives a note from a team member about a problem he is having. The note says, “This activity is driving me crazy and the manager of the accounting department won’t help me until the activity’s float is in jeopardy.” In addition, the project manager has e-mails, a team member walks in to the project manager’s office to tell her that a corrective action was implemented by a team member from the project management office, but was not documented. What should the project manager do NEXT?

  1. Add the implemented corrective action to the historical records, discuss the value documentation at the next team meeting, and smooth the team member with the accounting department problem.
  2. Report the documentation violation to the project management office, evaluate the security of the control limits, and review the e-mailing rules in the communications management plan
  3. Clarify the reasoning behind documentation being a problem, get the accounting department to assist the team member, and respond to the minor stakeholder
  4. Find out who caused the problem with the accounting department, respond to the minor stakeholder before responding to the other emails, and review the process listed in the communications plan for reporting concerns with the team member having the documentation problem.
Correct Answer










User Agreement| |Privacy Policy