IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You have designed an improvised system for a consumer product that could decrease repair cost for the consumer. Management is impressed with your idea, but has decided to wait until next year to implement it. What is the BEST thing to do?
  1. Advise government officials that there is a better alternative that could save the public money
  2. Wait until next year
  3. Go to one of your competitors with the idea in order to save consumers cost
  4. Tell everyone you come in contact with that you have a better design






Q2. Dave, a first-time project manager, was of the opinion that all training activities need to be planned. He discussed this with an experienced project manager who understood that some training was necessarily unplanned. Which of the following are good candidates for unplanned training?

  1. Training by observation, conversation, and project management appraisals
  2. Training by mentoring, on-the-job training, and online courses
  3. Training by conversation, coaching, and classroom training
  4. Training by mentoring, observation, and coaching
Correct Answer

Q3. A project manager has a project team consisting of people in four countries. The project is very important to the company, and the project manager is concerned about its success. The length of the project schedule is acceptable. What type of communication should he use?

  1. Informal verbal communication
  2. Formal written communication
  3. Formal verbal communication
  4. Informal written communication
Correct Answer

Q4. Your assistant project manager does the monthly earned value management (EVM) analysis, but falls ill before completing it. She has provided you with the following information: cost performance index (CPI) = 1.10, actual cost (AC) = US $800 million, planned value (PV) = US $890 million. How is the project going?

  1. The schedule is behind by 10 days.
  2. Both the schedule and the budget are better than planned
  3. There is enough money to support an offsite team outing
  4. You have no real concerns about either schedule or budget.
Correct Answer

Q5. You are designing a motor engine. During the design phase, you find that a technique required to develop the piston is a bit more advanced than the technology you currently possess. Although you can acquire this technology, it is too time consuming. On the other hand, there is a supplier that can provide you with the same component but at a higher cost. You are still discussing the options with your team members. Which technique are you using here?

  1. Select seller
  2. Source selection criteria
  3. Make or buy analysis
  4. None of the above
Correct Answer

Q6. A project manager is estimating project costs and needs to decide whether the estimates will include direct costs only or include indirect costs, as well. In which of the following phases does this decision need to take place?

  1. Define Scope
  2. Estimate Costs
  3. Plan Expenses
  4. Determine Budget
Correct Answer

Q7. Which of these is not an established Estimate Activity Durations technique?

  1. Three Point Estimating
  2. Parametric Estimating
  3. Analogous Estimating
  4. Critical Path Estimation
Correct Answer

Q8. You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally and you do not have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?

  1. Referent
  2. Expert
  3. Penalty
  4. Formal
Correct Answer

Q9. A project manager takes over an existing project, only to find that there are no quality standards. What part of the quality process should the project manager be in?

  1. Plan Quality
  2. Manage Quality
  3. Quality analysis
  4. Perform Quality Control
Correct Answer

Q10. A construction project requires that government environmental hearings be held prior to site preparation. What kind of dependency is this?

  1. Optional dependency
  2. Discretionary dependency
  3. Soft logic
  4. External dependency
Correct Answer










User Agreement| |Privacy Policy