In a double sampling plan, let d1 be the number of defects in the first sample and d2 be the number of defects in the second sample. Let c2 be the acceptance number for both samples. The condition for rejection is:
  1. D1+d2
  2. D1+d2>c2
  3. D1*d2>c2
  4. D1*d2






Q2. Self-inspection by the individual performing the work is used to achieve quality in a product. The advantages of self-inspection include ______________.

  1. minimization of end product repairs and material waste
  2. immediate feedback to permit adjustments to the process
  3. early identification of errors prior to further integration
  4. reduction in the number of end product inspections and tests
  5. all of the above
Correct Answer

Q3. The value of Var(3 - 4X) is:

  1. 5120 / 9
  2. 1280 / 81
  3. 5120 / 81
  4. 1280 / 9
Correct Answer

Q4. ______________ refers to general processes of improvement and encompasses discontinuous improvements

  1. Continuous improvement
  2. Continual improvement
  3. Constant improvement
  4. Consecutive improvement
Correct Answer

Q5. Which of the following is the correct combination of specifications while designing a control chart?

  1. Sample size, Process mean, specification limit
  2. Sample size, Frequency of sampling, specification limit
  3. Sample size, Frequency of sampling, Number of defects
  4. Sample size, Specification limit, process standard deviation
Correct Answer

Q6. Measurement accuracy is attained when...

  1. Different people get the same result when measuring the same item or characteristic.
  2. The same person taking multiple measurements on the same item or characteristic gets the same results every time.
  3. The measured value has little deviation from the actual value.
  4. When the resolution of the measurement instrument can give at least 5 distinct values in the range being measured.
Correct Answer

Q7. Tools and techniques used during the Quality Planning process include:

  1. Benchmarking
  2. all of the above
  3. Benefit / cost analysis
  4. Quality audits
  5. a and b
Correct Answer

Q8. When data is plotted on the control charts, the data is of two types: R and -bar. The R data represent points of a ______________ while the X-bar data represent points of a(n) ______________.

  1. real sample; simulated sample
  2. 100 percent sampling; 10 percent sampling
  3. sampling run; average of several runs
  4. random sampling; continuous sampling
  5. random sample; cross-matrix sample
Correct Answer

Q9. The majority of product defects could be prevented in most processes if manufacturers would do the following:

  1. Increase the use of acceptance control charts instead of standard three-sigma control charts
  2. Make a concerted effort to eliminate the potential for product defects in the design stage
  3. Create a quality control department
  4. A and B
  5. A and C
Correct Answer

Q10. Most quality problems

  1. are the result of management's lack of attention to potential quality improvement ideas
  2. originate in the quality department where the ultimate responsibility for quality rests
  3. originate on the shop floor because of waste and product rework
  4. could be eliminated if shop supervisors monitored their workers more closely
  5. A and B
Correct Answer