Question:

Based on the network diagram in the chart, the resource working on activity G is replaced with another resource with 50 percent of the productivity of the previous resource. How long will this project take?
Project Management PMP-5058.jpg
  1. 44
  2. 51
  3. 52
  4. 36






Q2. John has been assigned a task to build a facility where different types of bicycles can be produced. John builds this facility and hands it over to Andrew to run it. What is Andrew’s role?

  1. Project manager
  2. Program manager
  3. Operation manager
  4. Portfolio manager
Correct Answer

Q3. You are managing a multi-million dollar project that is a joint venture between your company and another organization. You have repeatedly tried to get the contact and the project charter finalized between the two organizations, but there has been a great deal of arguing over language and details. The project’s scope has been expanding, cost has been increasing, and the schedule has regularly been lengthening. You learn very suddenly that the project has been cancelled because the other organization withdrew its share of the funding for the project. What is the MOST likely reason that this occurred?

  1. Failure to understand the budgetary process
  2. Inadequate scope management
  3. Lack of sponsor commitment
  4. Poorly done initial cost-benefit analysis
Correct Answer

Q4. Due to corporate restructuring, the project sponsor, a major stakeholder, and the CEO have level the company. The project manager’s project is past the halfway point and the remaining members of the management team have been lukewarm toward the project. The new CEO does not place a high value on project management methodology, and the project team is nervous about its future. Under these circumstances, what is the project manager’s primary responsibility?

  1. Try to determine if the tea should continue to work on the project.
  2. Ensure that a conflict of interest does not compromise the legitimate interests of the customer.
  3. Interact with others in a professional manner while completing the project.
  4. Provide accurate and truthful representations in all project reports.
Correct Answer

Q5. After identifying a risk to your project, you determine that there is a high probability of risk occurring with a low consequence. What mitigation strategy is BEST to adopt?

  1. Eliminate the consequence of the risk.
  2. Avoid the risk
  3. Add the risk to the watch list
  4. Insure against the risk.
Correct Answer

Q6. Instead of celebrating the end of the project, the stakeholders are breathing a sigh of relief. None of them were confident the product would meet the end date. Which of the following is NOT one of the reasons this project had difficulty?

  1. Lack of payback period
  2. Lack of milestones
  3. Lack of a communications management plan
  4. Lack of a staffing management plan
Correct Answer

Q7. A team member notifies you that she has added extra functionality to the project. She tells you there was no impact on the cost or schedule. What should be done as a result of this change?

  1. Implement change control processes to track the change
  2. Understand what functionality was added
  3. Instruct the team member to remove the extra functionality
  4. Issue an approved change request
Correct Answer

Q8. You have the project management responsibility of a virtual team comprising team members from the same company who live in widespread geographic areas, employees who work from home offices and employees with mobility impairments. Virtual teams are formed as a result of which of the following processes?

  1. Acquire Resources
  2. Plan Resource Management
  3. Estimate Activity Resources
  4. Develop Schedule
Correct Answer

Q9. How many types of relationships between activities can be found on a precedence (AON) diagram?

  1. 4
  2. 3
  3. 2
  4. 1
Correct Answer

Q10. The sponsor of your facilities upgrade project has left the company to join another organization. Several weeks later, you are reviewing the business case for the project, and you find that there are several inconsistencies between what is stated in the business case and what is described in the project scope. Further research shows that the business case as a whole is based on inaccurate information. What do you do?

  1. Notify your project stakeholders immediately
  2. Add this to the risk log
  3. Update the requirements
  4. Call the sponsor for clarification
Correct Answer