IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following is not a basic input required to develop an effective project stakeholder engagement plan?
  1. Stakeholder register
  2. Enterprise environmental factors
  3. Organizational process assets
  4. Stakeholder engagement assessment matrix






Q2. As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between insufficient decomposition and excessive decomposition. When items are excessively decomposed, it leads to all the following except:

  1. Breaking the 100 percent rule
  2. Inefficient use of resources
  3. Nonproductive management effort
  4. Decreased efficiency when performing work
Correct Answer

Q3. Testing the entire population would:

  1. Take too long
  2. Provide more information than wanted
  3. Be mutually exclusive
  4. Show many defects.
Correct Answer

Q4. A Resource Breakdown Structure (RBS) breaks down the project by type of resources. The RBS is an example of a:

  1. Linear chart
  2. Matrix chart
  3. Flow chart
  4. Hierarchical chart
Correct Answer

Q5. If a project has a 60 percent chance of a $100,000 profit and a 40 percent chance of a $100,000 loss, the expected monetary value of the project is:

  1. $20,000 profit
  2. $40,000 loss
  3. $100,000 profit
  4. $60,000 loss
Correct Answer

Q6. The client has given you a project to construct a cold storage plant. Everything was going as planned, however, due to some unforeseen incidents, your project is delayed. The client is in a hurry and has threatened you with a large penalty if you are not able to complete the project on time. So, you started working hard to complete the project and avoid the fine. You are working overtime, bringing in more resources from other projects, and renting extra equipment; finally, you complete the project on time. This is an example of:

  1. Critical chain
  2. Fast tracking
  3. Crashing
  4. Resource leveling
Correct Answer

Q7. The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work the project team will execute to accomplish the project objectives and create required deliverables. The Create WBS process falls under which knowledge area?

  1. Project Schedule Management
  2. Project Integration Management
  3. Project Scope Management
  4. Project Cost Management
Correct Answer

Q8. You are in the process of planning human resources and developing the roles and responsibilities for your team members. Which of the following will you not address during this process?

  1. Role
  2. Authority
  3. Training
  4. Competency
Correct Answer

Q9. Warranty and inventory costs are going up, causing the project manager to worry about the costs of non-conformance. What is the BEST advice you can give the project manager?

  1. Increase scrap.
  2. Increase rework
  3. Perform a quality audit.
  4. Look for benchmarks.
Correct Answer

Q10. This project is chartered to determine new ways to extend the product life of one of the company’s medium-producing products. The project manager comes from the engineering department and the team comes from product management and marketing departments. The project scope statement and project planning are completed when a stakeholder notifies the team that there is a better way to complete one of the work packages. They even supply a technical review letter from their department proving that the new way to complete the work package will actually be faster than the old way. The project manager has had similar experiences with this department on other projects, and was expecting this to happen on this project. What is the FIRST thing the project manager should do?

  1. Contact the department and complain again about their missing the deadline for submission of scope.
  2. Look for how this schedule change will impact the cost to complete the work package and the quality of the product of the work package.
  3. See if there is a way to change from a matrix environment to a functional organization so as to eliminate all the interference from other departments.
  4. Ask the department if they have no other changes.
Correct Answer










User Agreement| |Privacy Policy