Project Management - Question 1:

Which of the following is not an input to the Conduct Procurements process?

  1. Proposal evaluation techniques
  2. Seller proposals
  3. Cost baseline
  4. Procurement management plan






Project Management- Q2. You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST?

  1. Add resources to the project.
  2. Evaluate the possibility of doing more activities in parallel.
  3. Negotiate for more time
  4. Explain to the customer that the project cannot be done on schedule.
Correct Answer


Project Management- Q3. You have joined an ongoing project. This project is in trouble, so you identify the issues which have the highest effect on the project, and now you are analyzing the reason for these issues. Which tool are you using now?

  1. Fishbone diagram
  2. Pareto diagram
  3. Scatter diagram
  4. Tornado diagram
Correct Answer


Project Management- Q4. Which of the following is Deming's method for continuous improvement?

  1. Plan-Act-Check-Do
  2. Plan-Do-Check-Act
  3. Check-Plan-Do-Act
  4. Plan-Check-Do-Act
Correct Answer


Project Management- Q5. Clear criteria for rewards and a planned system for their use promotes and reinforces desired behaviors in the project. Creating a recognition plan with established times for rewards ensures that recognition takes place and is not forgotten. This is usually part of the:

  1. Project Dashboard
  2. Resource Management Plan
  3. Company HR plan
  4. Communications Management Plan
Correct Answer


Project Management- Q6. Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. With the limited detail available to her, what would you expect the range of her estimate to be, and what would you call such an estimate?

  1. -25 to +25%, Absolute Cost
  2. -5 to +10%, Narrow
  3. -1 to +1%, Definitive
  4. -25 to +75%, Rough Order of Magnitude
Correct Answer


Project Management- Q7. Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?

  1. Estimated costs should be used to measure CPI.
  2. SPI should be used, not CPI
  3. Bottom-up estimating should have been used
  4. Past history was not taken into account.
Correct Answer


Project Management- Q8. During project executing, a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the pr manager involved in?

  1. Manage Quality
  2. Quality analysis
  3. Perform Quality Control
  4. Plan Quality
Correct Answer


Project Management- Q9. You are developing a product for your client. During the development of the product, the client has indicated that he needs some changes in the product, so you process his request. How do you manage changes in product specification?

  1. Change management
  2. Integration management
  3. Product management
  4. Configuration management
Correct Answer


Project Management- Q10. The project has been going well, except for the number of changes being. The project is being installed into even different department within the company and will greatly improve departmental performance when operational. There are 14 project management processes selected for use on this project. The project manager is a technical expert as well as having been trained in communications and managing people. Which of the following is the MOST likely cause of the project problems?

  1. The project manager was not trained in understanding the company environment.
  2. The project should have more management oversight since it will result in such great benefits to the company.
  3. The project should have used more of the project management processes.
  4. Some stakeholders were not identified
Correct Answer