IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

All of the following are components of cost management EXCEPT:
  1. Vendor bid analysis
  2. Analogous estimating
  3. Earned value management
  4. Estimate Activity Resources






Q2. A project manager is starting work on a complex project. There will be people from two different countries involved. The project sponsor is from a third country, and the work is being done on an expedited schedule in your country with 14 electrical engineers, 4 architects and their staffs, 3 mechanical engineers, and 2 maintenance experts. What should the project manager do to make sure all the work in this project is identified?

  1. Create a clear management plan, and put it in writing.
  2. Create a WBS with input from all parties involved.
  3. Identify the laws of each country involved.
  4. Create a scope control system.
Correct Answer

Q3. During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do?

  1. Make sure he has a good understanding of the activities and include the activities in the activity list.
  2. Ask the team member to explain why such activity would be needed to complete the work package
  3. Make sure the entire team agrees that the activities should be done
  4. Evaluate the impact of the change.
Correct Answer

Q4. A project manager new to project management is taking on a new project. When is the BEST time to help build the people working on the project into a team?

  1. During project initiating
  2. Before committing to a project cost estimate
  3. Throughout the project
  4. During project planning
Correct Answer

Q5. The WBS is a deliverable-oriented hierarchical decomposition of the work the project team must execute to accomplish the project objectives. This is created as part of:

  1. Project Integration Management
  2. Project Scope Management
  3. Project Procurement Management
  4. Project Schedule Management
Correct Answer

Q6. Which of the following is an example of a parametric estimate?

  1. Dollars per module
  2. Learning bend
  3. Bottom-up
  4. CPM
Correct Answer

Q7. A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar time. What is the FIRST thing you should do?

  1. Rebaseline the schedule to reflect the new date
  2. Analyze the critical path activities for potential to fast track or crash the schedule
  3. Document the lack of progress and associated issues to management
  4. Identify activities that required more time than planned 49
Correct Answer

Q8. The project was going well until the director of marketing discovered that two of her staff members were working different versions of the sampling plan, a product of your project. Which of the following BEST describes what needs the attention of the project manager on this project?

  1. Stakeholder management
  2. Resource allocation
  3. Staffing management plan
  4. Configuration management
Correct Answer

Q9. During the Manage Stakeholder Engagement process, a number of project documents might get updated. Which of the following project documents get updated the most during this process?

  1. Stakeholder register
  2. Risk register
  3. Project reports
  4. Project presentations
Correct Answer

Q10. A government agency has awarded your company a massive software project. This project has an early completion incentive, and your company has a policy of paying a bonus to the project manager if such an incentive is awarded. However, this particular government agency has a reputation for being extremely difficult to work with; there is a great deal of bureaucracy within this agency, and stonewalling and hostility toward contractors are common. The project manager will need to have excellent political skills to lead this project successfully. You have been asked to lead the project because of your expertise with this type of project. However, you have never worked within such a highly charged and political environment. What should you do?

  1. Decline the project citing lack of experience.
  2. Accept the project but disclose your lack of experience in this type of environment.
  3. Accept the project and request that a corporate liaison be assigned to your project.
  4. Accept the project.
Correct Answer










User Agreement| |Privacy Policy