IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Your new project to outsource work has been going badly. The project deliverables have changed three times, the functional managers keep removing people from the team, and the project schedule baseline has been adjusted four times in the first week. This is MOST likely due to the lack of:
  1. A staffing management plan
  2. A signed project charter
  3. Clear direction from the sponsor
  4. A scope management plan






Q2. You are managing a project with a budget of 500,000 USD, and 250,000 USD has been spent. Upon review, you observe that only 40% of the work has been completed. Your schedule says that you should have completed 50% of the work. What is estimate at completion (EAC)?

  1. 625,000 USD
  2. 500,000 USD
  3. 400,000 USD
  4. 375,000 USD
Correct Answer

Q3. One of the project objectives for your company was to acquire additional expertise completing a large scale design project. The project is mostly completed when your client terminates the contract. A change in their business means the work is no longer needed. What is the MOST effective thing to do?

  1. Stop work immediately
  2. Complete the project, but do not charge the client for the time
  3. Tell the client that work will stop after it is completed
  4. Move on to the Close Project or Phase process
Correct Answer

Q4. A project manager wants to use a group decision-making technique to generate, classify and prioritize requirements. Which of these is not a valid group decision-making technique?

  1. Plurality
  2. Singularity
  3. Majority
  4. Unanimity
Correct Answer

Q5. The organization’s strategy provides a strategic direction and performance parameters for identifying, selecting, and delivering the right mix of projects. If it is determined that some of the CEO’s favorite projects do not fully align with the business objective, the PMO manager must:

  1. Recommendation a realignment of the strategy
  2. Terminate the project
  3. Recommend a realignment of the project objectives
  4. Honor the CEO’s desires and execute the project
Correct Answer

Q6. Which of the following statements is correct:

  1. Project lifecycles and product lifecycles are interdependent.
  2. Project lifecycles are independent of product lifecycles.
  3. A product lifecycle is the same as a project lifecycle.
  4. The last lifecycle for a project is generally the product's retirement.
Correct Answer

Q7. A project manager for a small construction company has a project hat was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US 90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?

  1. Project manager
  2. Senior management
  3. Project sponsor
  4. Manager of the project management office
Correct Answer

Q8. You have just been assigned to take over a project that your management has told you is “out of control”. When you asked your management what the problems were, they had no specifics, but said that the project was behind schedule, over budget, and the client was dissatisfied. Which of the following should be of the MOST concern to you?

  1. The project is over budget and behind schedule
  2. There is very little documentation related to the project.
  3. The client is very dissatisfied with the project’s progress.
  4. Your management is looking for rapid and visible action on this project to rectify the problems.
Correct Answer

Q9. Sarah is about to start developing her project stakeholder engagement plan. She is currently gathering all the required inputs for this process. She has already created the stakeholder register and has gotten access to the organizational process assets and enterprise environmental factors. Which of the following inputs is also critical for the process?

  1. Expert Judgment
  2. Benchmarking
  3. Root cause analysis
  4. Project management plan
Correct Answer

Q10. Which of the following BEST describes when the baseline can be changed?

  1. Only under emergency conditions
  2. The original baseline is always maintained throughout the project
  3. With any approved changes
  4. When the project sponsor determines it is appropriate
Correct Answer










User Agreement| |Privacy Policy