IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

The role of each stakeholder is determined by:
  1. The stakeholder and the sponsor
  2. The project manager and the sponsor
  3. The team and the project manager
  4. The project manager and the stakeholder.






Q2. A team member tells the project manager that her activity will be delayed four weeks. The project manager investigates and determines that the delay will affect the project’s completion date. Who should approve the change?

  1. Change control board
  2. Project manager
  3. Team member
  4. Sponsor
Correct Answer

Q3. You are in the process of collecting and disseminating performance information to the stakeholders in the project. You want to predict the future performance of the project based on the current information. This performance information includes status reports, current status of risks, and summary of changes approved in the period. Which of the following methods will help you in predicting the future performance of the project?

  1. Forecasts
  2. A Pareto chart
  3. A run chart
  4. A Work Breakdown Structure
Correct Answer

Q4. The work breakdown structure can be an effective aid for the communication in which situation (s)?

  1. Internal within the project team
  2. Internal within the organization
  3. External with the customer
  4. Internal and external to the project
Correct Answer

Q5. When should a schedule baseline be created and used?

  1. At the beginning of the project and used to compare schedule performance on status reports
  2. At the end of the project and then used to measure team performance
  3. At the end of the project and included in the archive
  4. At the beginning of the project and used during the project to measure performance
Correct Answer

Q6. Michael and John are having some conflicts and they come to you. Since you are too busy and the problem is complex, you go with the midway of both parties and partially satisfy both of them. What conflict resolution technique are you using here?

  1. Accommodate
  2. Withdraw
  3. Collaborate
  4. Compromise
Correct Answer

Q7. A project team is in the design stage of a new mountain bicycle prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables?

  1. Benefit cost analysis
  2. Ishikawa diagram
  3. Design of experiments
  4. System flowchart
Correct Answer

Q8. The organization’s strategy provides a strategic direction and performance parameters for identifying, selecting, and delivering the right mix of projects. If it is determined that some of the CEO’s favorite projects do not fully align with the business objective, the PMO manager must:

  1. Recommendation a realignment of the strategy
  2. Terminate the project
  3. Recommend a realignment of the project objectives
  4. Honor the CEO’s desires and execute the project
Correct Answer

Q9. Kevin is assigned to a software development project that will start in the near future and is currently tailoring the PMBOK processes to satisfy the project’s specific needs. Kevin wants to introduce a new process, “Identify Key Deliverables”, to the existing six project scope management processes. Although he understands that project deliverables identification is already in the PMBOK scope management processes, he believes that having a dedicated process will stress the importance of determining and agreeing to key project deliverables. The best position for the new “Identify Key Deliverables” process should be between which of the following two processes?

  1. Define Scope and Create WBS
  2. Create WBS and Validate Scope
  3. Plan Scope Management and Collect Requirements
  4. Collect Requirements and Define Scope
Correct Answer

Q10. A project was awarded based on a competitive proposal. Management made a commitment that a few key team members would work on the project. When such assignments happen, they are:

  1. Bargaining agreements
  2. Schedule constraints
  3. Assignment risk
  4. Pre-assignments
Correct Answer










User Agreement| |Privacy Policy