Project Management - Question 1:

The project manager has a project that is three months behind but, surprisingly, markedly under budget. She has decided to try to make up some time, but needs to minimize the project risk. What is the BEST thing to do?

  1. Crash
  2. Fast track
  3. Redefine the scope
  4. Resource level






Project Management- Q2. Which of these is not a data gathering technique used in the Identify Risks process?

  1. Interviewing
  2. Checklists
  3. Brainstorming
  4. Delta technique
Correct Answer


Project Management- Q3. RACI stands for______________, ________________, ___________, _______________.

  1. Review, Analyze, Calculate, Implement
  2. Responsible, Actual, Complete, Informative
  3. Roles, Activities, Costs, Instructions
  4. Responsible, Accountable, Consult, Inform
Correct Answer


Project Management- Q4. A RACI chart is an example of a _________________.

  1. Network
  2. Flowchart
  3. Responsibility assignment matrix
  4. Hierarchical-type organization chart
Correct Answer


Project Management- Q5. Company A is developing a project similar to one it delivered nearly 12 months earlier. What is the MOST likely approach to defining project activities?

  1. Review organizational process assets
  2. Add similar, if not the same, skill sets to the project team
  3. Gather the team for a brainstorming session
  4. Hire a third party expert to avoid mistakes that were encountered during previous projects.
Correct Answer


Project Management- Q6. You are in the process of subdividing project deliverables and project work into smaller, more manageable parts so the project management team can get a structured vision of what has to be delivered. Which of the following is an output of this process?

  1. Scope baseline
  2. RBS
  3. Network diagram
  4. OBS
Correct Answer


Project Management- Q7. Two people are arguing about what needs to be done to complete a work package. If the project manager wants to know what is going, she should pay MOST attention to:

  1. What is said and when.
  2. What is being said, who is saying it and the time of day.
  3. Physical mannerisms and what is being said.
  4. The pitch and tone of the voices, and physical mannerisms.
Correct Answer


Project Management- Q8. What is the LAST thing to do in project closure?

  1. Complete the lessons learned
  2. Provide the client with all pertinent documentation
  3. Update the archives
  4. Release the team
Correct Answer


Project Management- Q9. You were asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget EXCEPT:

  1. Fixed costs.
  2. Sunk costs.
  3. Direct costs.
  4. Variable costs.
Correct Answer


Project Management- Q10. Which of the following is the primary output of the Develop Project Team process?

  1. Change requests
  2. Staffing management plan
  3. Team performance assessment
  4. Updated issue log
Correct Answer