IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You have just taken over a project from another project manager about six months into a 12-month project. As you get to know the staff on the project, you become aware that five staff members are relatives of the previous project manager. What do you do?
  1. Notify your project stakeholders there is a possibility that nepotism was behind some of the staffing decisions made on your project
  2. Check recruitment records of all employees
  3. Report the HR manager to PMI
  4. Interview these five employees






Q2. Which of the following statements about team-building activities is incorrect?

  1. It can be a five-minute agenda item in a status review meeting.
  2. It can be a professionally facilitated experience designed to improve interpersonal relationships.
  3. The objective of team-building activities is to help team members work individually and effectively.
  4. Informal communication and activities help in building trust and establishing good working relationships.
Correct Answer

Q3. There is a serious defect in the finished product of a project that was completed a few months ago, resulting in a recall campaign to recall the defective products. What would be the best classification for these types of costs?

  1. To complete performance index (TCP)
  2. Cost variance
  3. Cost of conformance
  4. Cost of nonconformance
Correct Answer

Q4. The methods used to transfer information among project stakeholders may vary significantly. A project team may apply different techniques and communication technologies to ensure effective and efficient communications. Which of the following must not be a factor to consider while choosing a communication technology?

  1. Urgency of the need for information
  2. Cheapest available technology
  3. Availability of technology
  4. Ease of use of technology
Correct Answer

Q5. The list of identified risks is found in the risk register. However, the overall high-level project risks is first listed in the:

  1. Scope statement
  2. Requirement document
  3. Project charter
  4. Risk management plan
Correct Answer

Q6. Which of the following is the BEST method to make reward systems MOST effective?

  1. Pay a large salary increase to the best workers
  2. Give the team a choice of rewards
  3. Make the link between performance and reward clear
  4. Present notification of rewards within the company.
Correct Answer

Q7. A team of experts come to your project and ask for approved procedures to verify your team is following these procedures. This is an example of which of the following?

  1. Quality control
  2. Manage quality
  3. Verify scope
  4. Control scope
Correct Answer

Q8. During risk planning, a team member comes to you and informs you about a risk. This risk was not important; therefore, you tell him to just note down the risk and you will manage this risk if it occurs. What risk response strategy you are using here?

  1. Mitigate
  2. Accept
  3. Avoid
  4. Exploit
Correct Answer

Q9. You have recently joined a new company as a project manager. While reviewing the procurement plans for a project you will be taking over, you see that the company is considering using one of the most expensive manufacturers to provide certain equipment required for the project. At your previous employer, you had used a different supplier for the same equipment and had paid significantly less. Without telling your boss, you now call that supplier for a quote. Have you violated the rule of keeping proprietary information confidential?

  1. Maybe. You need to talk to your boss first.
  2. No. There is no harm in sharing the information with your current employer, because you are no longer working for your old employer.
  3. Yes. The supply source is proprietary information, and you should not contact the supplier.
  4. You have not violated any rule.
Correct Answer

Q10. Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder involvement?

  1. Manage Stakeholder Engagement
  2. Monitor Stakeholder Engagement
  3. Manage Communications
  4. Monitor Communications
Correct Answer










User Agreement| |Privacy Policy