IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

Which of the following statements is correct?

  1. A collection of unrelated programs can constitute a portfolio.
  2. The scope of a portfolio is typically smaller than that of a program.
  3. A program is a group of unrelated projects.
  4. A program need not consist of projects.






Project Management- Q2. Which of these is not an Enterprise environmental factor that can influence the Plan Resource Management process?

  1. Organizational culture
  2. Lessons learned on organizational structures
  3. Marketplace conditions
  4. Facilities and resources
Correct Answer


Project Management- Q3. What might historical records from previous projects used as an input to the Define Activities process include?

  1. Activities
  2. Resources
  3. Costs
  4. Schedule
Correct Answer


Project Management- Q4. Although the business value is unique to each organization, each organization strives to attain business value for its activities. Which of the following does NOT create value for an organization?

  1. Escalation of commitment on projects involving significant sunk cost
  2. Effective management of ongoing operations
  3. Strategic alignment of project objectives
  4. Successful management of nonprofit business-related activities
Correct Answer


Project Management- Q5. Which of the following helps the project team to look at many sources from which project risks may arise in a risk identification exercise?

  1. Work Breakdown Structure
  2. Risk Breakdown Structure
  3. Risk register
  4. Issue log
Correct Answer


Project Management- Q6. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. What is the duration of this activity?

  1. 3
  2. 6
  3. 7
  4. 10
Correct Answer


Project Management- Q7. All of the following are parts of the Plan Quality process EXCEPT:

  1. Benchmarking
  2. Cost-benefit analysis
  3. Inspection
  4. Design of experiments.
Correct Answer


Project Management- Q8. You have signed a multi-year contract with a customer to complete a project for a fixed price. Since the duration of the contract is long, you have added a provision to adjust the price of the contract according to the market inflation. What kind of contract is this?

  1. FPIF
  2. FP-EPA
  3. Time and material
  4. CPIF
Correct Answer


Project Management- Q9. Which of these types of precedence relationships is least commonly used in the Precedence Diagramming Method?

  1. Start to Start
  2. Finish to Finish
  3. Finish to Start
  4. Start to Finish
Correct Answer


Project Management- Q10. Which factor would NOT be considered when choosing between two projects to undertake?

  1. Net present value (NPV)
  2. Benefit cost ratio (BCR)
  3. Payback period
  4. Law of diminishing returns
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed