During the project execution, a stakeholder comes to you and argues against a particular deliverable. You investigated it and found that this particular deliverable was based on his requirement. To prove this, what document will you show to him?
  • Scope statement
  • Requirement traceability matrix
  • Statement of work
  • Scope management plan