IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

What percentage of the total distribution is 3 sigma from the mean equal to?
  1. 68.26 percent
  2. 99.99 percent
  3. 95.46 percent
  4. 99.73 percent






Q2. Your manager is presenting a status report of all projects being run in his division. He reports that all projects are showing a positive CV. However, you know that your status reports for the last several weeks have been reporting a negative CV. What do you do?

  1. Do nothing.
  2. Offer to review all your manager's combined status reports before he presents them.
  3. Notify the appropriate management immediately.
  4. Ask your manager if that information was simply a typographical error.
Correct Answer

Q3. You have been producing ball bearings in large numbers. For this kind of process, what technique will you use to verify if the products are of the right quality?

  1. Inspection of all products
  2. Statistical sampling
  3. Inspection of the first three samples
  4. Inspection of the last three samples
Correct Answer

Q4. The highest point of Maslow’s hierarchy of needs is called:

  1. Physiological satisfaction
  2. Attainment of survival
  3. Need for association
  4. Esteem.
Correct Answer

Q5. Gordon is currently developing his project’s stakeholder management strategy. All enterprise environmental factors should be considered during this process. Which of the following enterprise environmental factors should be paid special attention during this process?

  1. Project templates
  2. The organization's culture and structure
  3. Commercial databases
  4. Lessons learned from past similar projects
Correct Answer

Q6. You are a project manager newly assigned to a large project for your organization. The project charter has been signed, and the stakeholders have been identified. What should you do next?

  1. Ask appropriate team members to submit WBS input
  2. Initiate the scope planning process
  3. Start the develop project management plan process
  4. Begin the activity definition process
Correct Answer

Q7. Which parts of the risk management process do not generally use organizational process assets as an input?

  1. Identify Risks and Perform Qualitative Risk Analysis
  2. Perform Qualitative and Quantitative Risk Analysis
  3. Perform Quantitative Risk Analysis and Plan Risk Responses
  4. Plan Risk Responses and Control Risks
Correct Answer

Q8. A control chart helps the project manager:

  1. Focus on the most critical issues to improve quality
  2. Focus on stimulating thinking
  3. Explore a desired future outcome
  4. Determine if a process is functioning within set limits.
Correct Answer

Q9. The Quality Policy is the intended direction of a performing organization with regard to quality. However, as a project manager in a performing organization, you find the organization lacks a formal quality policy. What should you do in such a case?

  1. The project management team does not need to develop a quality policy since the performing organization does not have one.
  2. The project management team needs to obtain the quality policy from the customer.
  3. A quality policy is nice to have but is not required for every project.
  4. The project management team will need to develop a quality policy for the project.
Correct Answer

Q10. Documents that serve as historical records for future projects are archived:

  1. Throughout the project
  2. Before the end of planning
  3. Before the end of execution
  4. During closure
Correct Answer










User Agreement| |Privacy Policy