IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

Which of the following is not a project competing constraint?

  1. Budget
  2. Procurement
  3. Risk
  4. Resource






Project Management- Q2. Which of the following is true of the Estimate Activity Durations process?

  1. Estimates should always indicate the range of possible results
  2. Estimates should be made by resource managers in order to increase the accuracy of the estimates.
  3. Historical information is too old to use in estimating
  4. Critical paths should be taken into account when an activity is first estimated.
Correct Answer


Project Management- Q3. A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:

  1. Create a project scope statement
  2. Confirm that all the stakeholders have had input to the scope
  3. Analyze project risk
  4. Begin work on a project management plan
Correct Answer


Project Management- Q4. A control chart should always contain:

  1. Upper and lower warning limits
  2. The moving average
  3. Upper and lower control limits
  4. Upper and lower specification limits
Correct Answer


Project Management- Q5. Chris is managing a construction project. The project team is currently developing the “as built” construction drawings to be supplied to the client as required by the contract. Which of the following phases is Chris’ project most likely in?

  1. Initiating
  2. Planning
  3. Closing
  4. Executing
Correct Answer


Project Management- Q6. Which of the following BEST describes product analysis?

  1. Working with the customer to determine the product description.
  2. Mathematically analyzing the quality desired for the project.
  3. Gaining a better understanding of the product of the project in order to create the project scope statement.
  4. Determining if the quality standard on the project can be met.
Correct Answer


Project Management- Q7. What is a common result of poor project planning?

  1. Wasted effort
  2. Lost time
  3. Increased cost
  4. All of the above
Correct Answer


Project Management- Q8. You are taking over a project during the planning process group and discover that six individuals have signed the project charter. Which of the following should MOST concern you?

  1. Who will be a member of the change control board
  2. Spending more time on configuration management
  3. Getting a single project sponsor
  4. Determining the reporting structure
Correct Answer


Project Management- Q9. Analysis of project spending against project budget and calculation of the percentage complete of tasks currently underway are examples of:

  1. Control Chart
  2. PERT analysis
  3. Performance reviews
  4. Expert judgment
Correct Answer


Project Management- Q10. The transition from one phase to another within a project's lifecycle (e.g., from design to manufacturing) is typically marked by:

  1. Kill point
  2. Monte Carlo
  3. Constraint
  4. Decision tree
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed