IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Business value is also defined as the aggregate of all tangible and intangible elements of the business. Which of the following is NOT an example of a tangible business element?
  1. Monetary assets
  2. Goodwill
  3. Fixtures
  4. Stockholder equity






Q2. At the end of a project, what will your schedule variance be equal to?

  1. Zero
  2. Equal to the total PV
  3. One
  4. Equal to the total EV
Correct Answer

Q3. A project manager was assigned to a project when the project charter was in development. Which of the following is an input that the project manager will use to develop the project charter?

  1. Make-or-Buy analysis
  2. Organizational Process Assets
  3. Project Acceptance Criteria
  4. Project Scope Statement
Correct Answer

Q4. Which of the following can NOT be used to measure business value?

  1. Customer satisfaction
  2. Revenue growth
  3. Market share
  4. Expected monetary value
Correct Answer

Q5. During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:

  1. Let the sponsor know of the stakeholders’ request
  2. Evaluate the impact of adding the scope
  3. Tell the stakeholders the scope cannot be added
  4. Add the work if there is time available in the project schedule
Correct Answer

Q6. Projects are often started as a result of an external factor such as market demand for a new product, a new legislative or regulatory mandate, or a change in technology. This results in the creation of ______ by an entity or organization external to the project.

  1. The project charter
  2. The WBS
  3. The project budget
  4. The RACI chart
Correct Answer

Q7. Three items from the issue log have been assigned to a team member. However, no action has been taken by the agreed-upon due date. After three calls to the team member, the work is finally completed. Which of the following is the BEST preventive action to take NOW?

  1. Remove the team member from the team if possible
  2. Meet with the team member to uncover the reasons why there were problems
  3. Make sure the action item list is distributed to all the right parties
  4. Make sure items assigned in the action item list are accepted by the team members they are assigned to.
Correct Answer

Q8. You have been hired as a consultant for a project that is in trouble. You meet the project manager and ask several questions regarding the project budget, the project end date, etc. The project manager was not able to answer some of these questions properly, so you decided to verify them yourself. What document will you refer to in order to verify such facts?

  1. Project management plan
  2. Cost and schedule baselines
  3. Project charter
  4. Performance report
Correct Answer

Q9. Theory X postulates that people:

  1. Are motivated by pay
  2. Have expectations
  3. Need to be watched every second
  4. Can direct their own efforts.
Correct Answer

Q10. An increase in quality can result in increased productivity, increased cost effectiveness, and:

  1. Decreased cost risk
  2. Decreased morale
  3. Lower customer satisfaction
  4. Increased risk.
Correct Answer










User Agreement| |Privacy Policy