IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You need to hire several subject matter experts for your project. Time is limited and the scope of work is also not very clear. In this situation what kind of procurement contract will you utilize to hire experts?
  1. Cost plus fixed fee
  2. Firm fixed price
  3. Fixed price economic price adjustment
  4. Time and material






Q2. You are in charge of a project developing a complex product that does not resemble anything your organization has done previously. You are using a resource to develop this product, which is in high demand elsewhere in your organization. The project’s timeframe is very aggressive. In order to meet the schedule, only a limited amount of testing is done. Once the testing is completed, the resource is released. The product works fine when being tested, but in production, it performs poorly. This results in a substantial amount of rework and extra costs to reacquire the resource on an overtime basis. Which of the following BEST describes why this project had problems?

  1. Poor quality management
  2. Poor reporting
  3. Poor risk identification
  4. Poor resource management
Correct Answer

Q3. Your project is being completed in another country. It is going reasonably well and is ahead of the cost projections when one of the local officials informs you he will make sure the project work stops unless you pay him $50. What is the BEST thing to do?

  1. Make the payment
  2. Offer to pay more than the requested amount to get more support from the official in the future.
  3. Offer to pay a smaller amount to discourage future requests for larger amounts.
  4. Do not make the payment 26
Correct Answer

Q4. Which of the following MUST be an agenda item at all team meetings?

  1. Discussion of project risks
  2. Status of current activities
  3. Identification of new activities
  4. Review of project problems.
Correct Answer

Q5. The customer wants to expand the product scope after the performance measurement baseline has been established. Which document will the customer need to submit?

  1. Change request
  2. Project scope statement
  3. Performance measurements
  4. Activity attributes 02
Correct Answer

Q6. You have met with your project sponsor who told you that you must complete the project by the end of the year, no exceptions. This should be included in the project scope statement as a:

  1. Project Constraint
  2. Project Boundary
  3. Project Acceptance Criteria
  4. Project Assumption
Correct Answer

Q7. You have a project with a cost of 10,000 USD, and the duration is 10 months. Five months have passed, 45% of the work is completed and you have spent 5,500 USD. The value of this 45% of the work is known as:

  1. Planned value
  2. Earned value
  3. Actual cost
  4. Schedule variance
Correct Answer

Q8. If a risk event has a 90 percent chance of occurring, and the consequences will be US $10,000, what does US $90,000 represent?

  1. Risk value
  2. Present value
  3. Expected monetary value
  4. Contingency budget
Correct Answer

Q9. Your project is going full steam and to prepare a monthly report you collect some data and give it to John who is your team member. You ask him to provide you with work performance information. He analyzes the information, compiles the data, and gives you the requested information which includes the status of deliverables, the number of change requests, implementation status for change requests, and forecasted estimates to complete. Among this information, which does not represent the information you requested?

  1. Number of change requests
  2. Status of deliverables
  3. Forecasted estimates to complete
  4. Implementation status for change requests
Correct Answer

Q10. Which of the following is the BEST method to make reward systems MOST effective?

  1. Pay a large salary increase to the best workers
  2. Give the team a choice of rewards
  3. Make the link between performance and reward clear
  4. Present notification of rewards within the company.
Correct Answer










User Agreement| |Privacy Policy