Question:

According to the project manager’s earned value (EV) analysis of a software development project on June first, the cost performance index (CPI) computes to 1.0 and the schedule variance (SV) is zero. On June third, the banks of the nearby river overflow and flood the development computer room, shutting down all operations for two weeks. This project has been struck by a (n):
  1. Unknown unknown risk.
  2. Known unknown risk.
  3. Known risk.
  4. Foreseen risk.






Q2. The primary customer of a project has requested an application change during user testing. As project manager, how should you BEST address this issue?

  1. Develop a risk mitigation plan.
  2. Create a formal change request.
  3. Inform the project sponsor of changes to scope, cost and schedule.
  4. Ensure the scope change compies with all relevant contractual provisions.
Correct Answer

Q3. Which of the following BEST describes why quality is planned in and not inspected in?

  1. It reduces quality and is less expensive.
  2. It improves quality and is more expensive
  3. It reduces quality and is more expensive
  4. It improves quality and is less expensive
Correct Answer

Q4. Your boss has asked you for a cost baseline for the project, but it is early in the project management process and there is very little project information. In this circumstance, what is the BEST way to estimate this project?

  1. Extrapolate from historical data
  2. Ask the team for estimates of each activity
  3. Provide a rough order of magnitude estimate
  4. Calculate an estimate using the schedule model
Correct Answer

Q5. You are sitting in a group discussion with 13 stakeholders and collecting ideas. Now you are in the final stage and are selecting the final idea. As there are many ideas, you decide to vote. After voting you see that a particular idea receives 7 votes, so you go with that option. What kind of decision making is this?

  1. Unanimity
  2. Majority
  3. Plurality
  4. Dictatorship
Correct Answer

Q6. A team member complains to the project manager that another team member has once again failed to provide necessary information. The project manager meets with both team members to uncover the reason for the problem. This is an example of:

  1. Withdrawal
  2. Confronting
  3. Compromising
  4. Smoothing.
Correct Answer

Q7. During the project execution, some people stole your consumables. You did not identify this threat earlier, though you were able to manage the situation through a workaround. This risk did not have much of an impact on your cost baseline but the schedule was impacted. Management is aware of the issue and to get the complete picture they insist you provide them the performance report. Which of the following information will you provide to them?

  1. Status of deliverables
  2. Actual cost, actual duration, etc.
  3. Milestones status
  4. Memos
Correct Answer

Q8. All of the following are inputs to the Validate Scope process EXCEPT:

  1. Work breakdown structure
  2. Project scope statement
  3. WBS dictionary
  4. Inspection
Correct Answer

Q9. The buyer asks the project manager for the status of the project that his team is working on. What is the BEST way to determine the status of a project?

  1. Compare the project performance against the project baselines
  2. Compare the earned value to the planned value
  3. Compare the project performance against the integrated change control plan.
  4. Compare the number of people used on each work package to the planned number to be used.
Correct Answer

Q10. The project charter is a document which initiates the project, establishes your authority and contains some high-level information. Which of the following information will not be included in the project charter?

  1. Project purpose
  2. High-level requirements
  3. High-level risks
  4. Name of the competitor
Correct Answer