IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Daniel is managing the development of an e-commerce website for his organization. Daniel enjoys coercive powers. He has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must:
  1. Influence team members to support the project manager's decisions
  2. Support the team members to challenge the project manager's decisions
  3. Negotiate with team members to achieve the project objectives
  4. Remain neutral and conduct the meetings






Q2. Although it is highly recommended that lessons learned are captured and documented throughout the project lifecycle, lessons learned are finalized during project closure. At this stage, responses to high-level questions may be gathered and documented. Which of the following is not an appropriate question to ask at this stage?

  1. What were the top significant project successes?
  2. How relevant the historic lessons learned were to this project during execution?
  3. What obstacles or unanticipated circumstances made it difficult to complete the project?
  4. What should have been done differently in this project?
Correct Answer

Q3. The termination clause and alternative dispute resolution (ADR) mechanism for each procurement in a project is in the:

  1. Scope Statement
  2. Agreement
  3. Resource Calendars
  4. Source Selection Criteria
Correct Answer

Q4. You are in charge of a project developing a complex product that does not resemble anything your organization has done previously. You are using a resource to develop this product, which is in high demand elsewhere in your organization. The project’s timeframe is very aggressive. In order to meet the schedule, only a limited amount of testing is done. Once the testing is completed, the resource is released. The product works fine when being tested, but in production, it performs poorly. This results in a substantial amount of rework and extra costs to reacquire the resource on an overtime basis. Which of the following BEST describes why this project had problems?

  1. Poor quality management
  2. Poor reporting
  3. Poor risk identification
  4. Poor resource management
Correct Answer

Q5. When should a schedule baseline be created and used?

  1. At the beginning of the project and used to compare schedule performance on status reports
  2. At the end of the project and then used to measure team performance
  3. At the end of the project and included in the archive
  4. At the beginning of the project and used during the project to measure performance
Correct Answer

Q6. Which of the following is needed to develop a project schedule?

  1. Lessons learned
  2. Network diagram
  3. Completion of the Verify Scope process
  4. Completion of the Control Schedule process
Correct Answer

Q7. On-demand scheduling is one of the techniques used in agile projects. This type of scheduling relies on:

  1. A schedule that was developed previously for the development of the project increments.
  2. Discretionary dependencies that cannot be changed by the project team.
  3. Skills of the project manager rather than the skills of the team.
  4. A backlog or intermediate queue of work to be done.
Correct Answer

Q8. The best practice to gather and document lessons learned is during weekly progress meetings. The agenda can have a lessons-learned brainstorming item at the end of these meetings. You can ask team members to put forward their recommendations, but it is always better to adopt a more structured way to gather lessons learned. Which of the following approaches will ensure you capture important lessons learned on your project?

  1. Planning risk responses
  2. Determining estimate to complete
  3. Review of project variances
  4. Signing off on the minutes of the meeting
Correct Answer

Q9. A project manager is using a Risk Diagramming technique that is a graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes. This would be:

  1. A system flow chart
  2. An Influence Diagram
  3. A Pareto chart
  4. Histogram
Correct Answer

Q10. You are managing two projects. The first project is to design and construct a school building, and the second project is to construct an office building for your company's employees. What is your current role?

  1. Project manager
  2. Program manager
  3. Portfolio manager
  4. None of the above
Correct Answer










User Agreement| |Privacy Policy