IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Your employee is three days late with a report. Five minutes before the meeting where the topic of the report is to be discussed, she hands you the report. You notice some serious errors in it. What should you do?
  1. Cancel the meeting and reschedule when the report is fixed.
  2. Go to the meeting and tell the other attendees there are errors in the report
  3. Force the employee to do the presentation and remain silent as the other attendees find the errors.
  4. Cancel the meeting and rewrite the report yourself.






Q2. Change requests are an output of which processes?

  1. Manage Project Team and Report Performance
  2. Manage Stakeholder Expectation and Determine Budget
  3. Define Scope and Plan Communications
  4. Plan Procurements and Perform Qualitative Risk Analysis.
Correct Answer

Q3. The project manager on a large software installation project is working with her team on a critical set of activities. They are working late on Saturday night. Circumstances create the wherein the project manager must decide to change the schedule that will push the end date of the project out two weeks. What has MOST likely happened?

  1. An emergency project change has taken place.
  2. Scope creep has occurred
  3. A status change to the implementation has taken place.
  4. Risk assessment failure has taken place
Correct Answer

Q4. Skills such as empathy, influence, creativity, and group encouragement are valuable assets when managing the project team. These skills are often referred to as ______________.

  1. Effort-based management
  2. Feedback-based skills
  3. Ad hoc skills
  4. Soft skills
Correct Answer

Q5. The stakeholder engagement plan is developed early during project planning phase. However, as the project moves into its execution phase, project stakeholders’ needs, interests and/or influence might change. If a significant change happens, what should the project manager do?

  1. Refer the issue to the project sponsor
  2. Hold all project communications until the issue has a resolution
  3. Seek expert judgment from the project sponsor
  4. Revisit the Plan Stakeholder Engagement process
Correct Answer

Q6. Uncontrolled project scope changes are often referred to as ________ .

  1. Scope creep
  2. Scope verification
  3. Value Added Scope
  4. Scope control
Correct Answer

Q7. Large organizations typically manage a wide range of projects; from small projects to large initiatives requiring long-term commitments. Which of the following factors can be used in scaling such projects:

  1. Team size, geographical distribution, regulatory compliance, organizational complexity, technical complexity, and funds availability.
  2. Team size, geographical distribution, regulatory compliance and organizational complexity.
  3. Team size, geographical distribution and regulatory compliance.
  4. Team size, geographical distribution, regulatory compliance, organizational complexity and technical complexity.
Correct Answer

Q8. What percentage of the total distribution is 3 sigma from the mean equal to?

  1. 68.26 percent
  2. 99.99 percent
  3. 95.46 percent
  4. 99.73 percent
Correct Answer

Q9. Which of the following statements about the management of risks in a project is incorrect?

  1. The effect of various risks on project scope, cost, and quality is numerically analyzed in the perform quantitative risk analysis process.
  2. Positive risks are mitigated during the plan risk responses process.
  3. Stakeholder analysis is performed during the plan risk management process.
  4. Risk report is produced during the perform quantitative risk analysis process.
Correct Answer

Q10. The current update to the schedule performance report shows no schedule variance. Based upon this report, you tell the client that the project is on time. However, your team members know that you just missed a major milestone and the project will not meet its startup date. This is an indication of poor:

  1. Communications planning.
  2. Scope planning.
  3. Team trust.
  4. Schedule planning.
Correct Answer










User Agreement| |Privacy Policy