Quality - Question 1:

Pattern in control charts which show the tendency to cluster around central line is termed as:

  1. Stratification
  2. Mixture
  3. Cyclic pattern
  4. Shift in process level






Quality- Q2. If the Average outgoing Quality is plotted against the Incoming Fraction Defective, the Average Outgoing Quality Limit is the ______________ point.

  1. Highest
  2. Lowest
  3. Middle
  4. Cannot be determined
Correct Answer


Quality- Q3. Identify the cost not likely to reduce as a result of better quality.

  1. Maintenance costs
  2. Inspection costs
  3. Scrap costs
  4. Warranty and service costs
Correct Answer


Quality- Q4. A fishbone diagram is also known as a .______________

  1. cause-and-effect diagram
  2. poka-yoke diagram
  3. Kaizen diagram
  4. Taguchi diagram
Correct Answer


Quality- Q5. The major purpose of the Control Phase in DMAIC is to:

  1. Identify root causes
  2. Determine long term solutions
  3. Maintain the gains made with implemented solutions
  4. Calculate Cp and Cpk
Correct Answer


Quality- Q6. Consider for a process in control, the value of alpha is .0015. What is the value of the average run length?

  1. 666 ( 1/alpha gives us an estimate of average run length)
  2. 555
  3. 444
  4. None of the above
Correct Answer


Quality- Q7. A planning method designed to show the tasks associated with a project, the personnel responsible for completing the tasks and the timelines allowed

  1. Pareto chart
  2. Gantt chart
  3. Microsoft Project
  4. Check sheet
Correct Answer


Quality- Q8. Juran's Quality trilogy emphasizes the roles of quality planning, quality control and ______________

  1. Quality Definition
  2. Quality enhancement
  3. Quality improvement
  4. quality maintenance
Correct Answer


Quality- Q9. Mistake proofing of process is done in the ______________ stage of DMAIC.

  1. Define
  2. Measure
  3. Improve
  4. Control
Correct Answer


Quality- Q10. For a c chart, the OC curve plots the ______________ against ______________.

  1. Probability of Type 2 error, true mean number of defects
  2. Probability of Type 1 error, true mean number of defects
  3. Probability of Type 1 error, true total number of defects
  4. Probability of Type 2 error, true total number of defects
Correct Answer











EXPLORE IRGST

What Are You Looking For?

Find the resources that match your interests and professional goals.

YOUR GROWTH STARTS HERE

Make Your Next Move a Better One.

Whether you want to test your abilities, prepare for a new opportunity, or keep learning, IRGST is here to help you move forward.

Start Exploring
User Agreement| |Privacy Policy
© 2026 - Tag&Link