Question:

A project manager analyzed the project’s communication requirements and decided that 10 out of the 30 stakeholders in the project would only need voicemail updates of certain information. This type of communication is:
  1. Push communication
  2. Pull communication
  3. Interactive communication
  4. On-demand communication






Q2. You have just been assigned as project manager for a large telecommunications project. This one-year project is about halfway done. The project team consists of five sellers and 20 of your company’s employees. You want to understand who is responsible for doing what on the project. Where would you find such information?

  1. Responsibility assignment matrix
  2. Resource histogram
  3. Bar chart
  4. Project organization chart.
Correct Answer

Q3. During a team meeting, the team has been arguing about the method of integration for over 20 minutes without getting anywhere. The project manager reschedules the issue for the next team meeting. This is an example of:

  1. Compromising
  2. Forcing
  3. Smoothing
  4. Withdrawal.
Correct Answer

Q4. A project team member has been having a big disagreement with another team member for over two months when the other team members become involved. The issues are complex, but you have specific experience in the area and know what needs to be done. The BEST choice would be to:

  1. Make the decision yourself
  2. Strive for fair resolution of the issue
  3. Ask the other team members to stay out of the issue
  4. Bring the team together and work out the issue to a win-win solution.
Correct Answer

Q5. A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do?

  1. Fix the problem as soon as possible.
  2. Allow the schedule to slip by cutting cost.
  3. Allow cost to increase by fixing the root cause of the problem.
  4. Allow risk to increase by cutting cost.
Correct Answer

Q6. During the Identify Risks process, a project manager made a long list of risks identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers had been identified. Later, in the Plan Risk Responses process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong?

  1. More people should be involved in the Plan Risk Responses process
  2. Triggers are not identified until the Identify Risks process.
  3. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved.
  4. The project manager should have created workarounds
Correct Answer

Q7. Why must the Validate Scope process be completed in a project?

  1. To obtain scope documents from recent similar projects for benchmarking
  2. To determine whether the scope is at the correct complexity level
  3. To obtain formal acceptance of deliverables by the customer or sponsor
  4. To ensure the project team is all aware of the scope
Correct Answer

Q8. While conducting interviews for a project manager position, you notice that your classmate is one of the prospective candidates. What should you do immediately?

  1. Encourage your classmate by offering some tips
  2. Resign from the interview panel
  3. Remove your classmate from the list
  4. Inform the interview panel of the relationship
Correct Answer

Q9. You have been assigned as a project manager for a project which was terminated a few years earlier due to some government regulations. Now you reviewing this document to start again. This document is an example of:

  1. Enterprise environment factor
  2. Organizational process assets
  3. Stakeholder analysis
  4. Control scope
Correct Answer

Q10. You are managing a project with a budget of 500,000 USD, and 250,000 USD has been spent. Upon review, you observe that only 40% of the work has been completed, your schedule says that you should have completed 50% of the work. What will be estimate to complete (ETC)?

  1. 625,000 USD
  2. 500,000 USD
  3. 400,000 USD
  4. 375,000 USD
Correct Answer