IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

In an underground highway construction project, the project stakeholders have suggested many changes to the project scope. You had already defined the cost baseline in your project, and you would like to revisit the baseline to see how these changes might affect the overall cost of the project. You start an impact analysis to determine the impact and inform the concerned stakeholders of all approved changes and the corresponding costs. You perform these activities in which process?
  1. Control Scope
  2. Monitor Risks
  3. Control Costs
  4. Monitor Communications






Q2. You are the project manager for a $3,000,000 product development project. Your project is well into the executing process group and remains on time, on budget and no specification. This morning your project sponsor called to express concern about he project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mail is too impersonal and verbal updates are preferred. This situation suggests problems with which of the follow project management processes?

  1. Plan Communications
  2. Distribute Information
  3. Report Performance
  4. Stakeholders Management
Correct Answer

Q3. Caitlin’s project is behind schedule. She is planning to crash the project by allowing overtime to the project team. This approach can bring additional risks to the project. Which of the following is not a valid risk in this scenario:

  1. The profit margin might decrease.
  2. Risk of employee attrition might increase.
  3. Risk of errors and/or rework might increase.
  4. The project’s acceptance criteria might get updated.
Correct Answer

Q4. The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with all the stakeholders to find out why there were changes and to discover any more. The project work has quieted down when a team member casually mentions to the project manager that he added functionality to a product of the project. Do not worry he says, “I did not impact time, cost, or quality!”

  1. Ask the team member how the need for functionality was determined
  2. Hold a meeting to review the team member’s completed work
  3. Look for other added functionality.
  4. Ask the team member how he knows there is no time, cost, or quality impact.
Correct Answer

Q5. A stakeholder register contains all the information about the stakeholders. Which of the following is not included in the stakeholder register?

  1. List of stakeholders
  2. Stakeholders’ classification
  3. Responsibility of assignments
  4. None of the above
Correct Answer

Q6. You have found you do not yet have an accurate estimate of the number and skill levels of resources needed for the scheduled activity Build Racks for Data Center. You need this estimate for presentation to your Human Resources department later in the week. You have decided to decompose the Build Racks for Data Center activity into smaller components such as take equipment out of box, review equipment for completeness, build frame, and install rails. Then you plan to estimate the resources for each smaller component and combine those estimates into an aggregate. This is an example of:

  1. Aggregate Estimating
  2. Alternative Analysis
  3. Bottom-up Estimating
  4. Rolling Wave Estimating
Correct Answer

Q7. The financial systems project has a relatively high profile in the organization and has received great support from the sponsor. There are over 230 activities on the project, and a few have remained relatively large due to the nature of the work to be accomplished. One of these larger activities has an estimate to complete (ETC) that is longer than planned. If the project manager wants to look at non-value-added activities that might be causing the delay, the manager should:

  1. Measure using quality metrics
  2. Complete process analysis
  3. Perform a quality audit
  4. Use a Pareto chart
Correct Answer

Q8. After the kickoff meeting, two team members engage in a casual conversation about the project objectives and deliverables. It is clear they heard different messages during the meeting. One team member is so adamant that the other team member give up arguing the point. After talking to the project manager, the second team member confirms that the first team member is mistaken. At this point, what is the BEST course of action?

  1. The second team member should send the other team member an e-mail describing what he discovered.
  2. At the next project meeting, the team member should ask the mistaken team member to describe his interpretation so the project manager can get everyone on the same page.
  3. The project manager should send out an e-mail to the team restating the project objectives and deliverables.
  4. At the next project meeting, the project manager should spend time reviewing the documented project scope statement for the purpose of identifying this and other false assumptions.
Correct Answer

Q9. A project to design and build a new aircraft is cancelled after the project has been underway for some time. What process is employed to document what work was done and to what extent it was completed?

  1. Validate Scope
  2. Control Scope
  3. Control Quality
  4. Close Project or Phase
Correct Answer

Q10. A ranking of risk and a list of risks for additional analysis are all outputs of which process of risk management?

  1. Identify Risks
  2. Perform Qualitative Risk Analysis
  3. Perform Quantitative Risk Analysis
  4. Plan Risk Responses.
Correct Answer










User Agreement| |Privacy Policy