IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A first-time project manager wanted to have a “perfect project.” This manager informed the customer that this project would not accept change requests of any kind and that the scope would need to be defined precisely at the very start of the project. The customer agreed to this request. What would your comment on this situation be?
  1. The is a good example of how the project management team can decide what is and what is not necessary for the project. Not allowing changes is a good way of ensuring that the project meets requirements as detailed in the project scope.
  2. This is unrealistic and impractical. Change is inevitable and rather than look at a 'no change' project, it would be more in the project interests to plan for a robust change control process.
  3. This indicates that the project manager is very aggressive and is likely to take the project to successful completion. Since he has announced the 'no change requests' policy, the customer manager can no longer request changes.
  4. This is unrealistic and impractical. The project manager should not have announced his intentions to the customer. He should have had an unofficial policy of rejecting all change requests.






Q2. You are in the define scope process and defining the detailed scope of the product and the project. This process helps you define the description of product, service or result and define boundaries and tells you about requirement inclusion and exclusion. Which of the following is not an outcome once the process ends?

  1. Acceptance criteria
  2. Project exclusions
  3. Risk register update
  4. Stakeholder register update
Correct Answer

Q3. What percentage of the total distribution is 3 sigma from the mean equal to?

  1. 68.26 percent
  2. 99.99 percent
  3. 95.46 percent
  4. 99.73 percent
Correct Answer

Q4. Many quality problems plagued a project. The quality of the work products deviated considerably from specifications. The project manager decided to do a root cause analysis. What activities does a root cause analysis include?

  1. Discovery of the underlying causes of a problem
  2. Problem Identification and discovery of the underlying causes of a problem
  3. Identification of a problem
  4. Problem identification, discovery of the underlying causes of a problem, and development of preventive actions
Correct Answer

Q5. You see an opportunity if you complete the project ahead of time: you may get a new project. Therefore, you try to complete the project early, but due to lack of resources, you are only able to shorten the duration of a few activities by starting the parallel or partially-parallel. Which risk response strategy are you employing here?

  1. Exploit
  2. Mitigate
  3. Enhance
  4. Accept
Correct Answer

Q6. Which of the following BEST describes the Validate Scope process?

  1. It provides assurances that the deliverable meets the specifications, is an input to the project management plan, and an output of Perform Quality Control.
  2. It ensures that the deliverable is completed on time, ensures customer acceptance, and shows that the deliverable meets specifications.
  3. It ensures customer acceptance, shows that the deliverable meets specifications, and provides a chance for differences of opinion to come to light.
  4. It is an output of Perform Quality Control, occurs before Define Scope, and ensures customer acceptance.
Correct Answer

Q7. During the course of the project, the project management team developed a forecast for the estimate at completion (EAC) based on the project performance. Which of the following statements about EAC is correct?

  1. The EAC forecast based on the Bottom-up estimate to complete (ETC) requires a new estimate.
  2. The EAC forecast is best estimated using the estimate to complete (ETC) work performed considering both SPI and CPI factors.
  3. The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the present CPI.
  4. The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the budgeted rate.
Correct Answer

Q8. During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takes on a negative variance. Which analysis method is the project manager likely to use as a measurement tool to validate this information?

  1. EV-PV
  2. EV/AC
  3. EV/PV
  4. EV-AC 75
Correct Answer

Q9. You are working on a project to build a production line to produce round balls. During the inspection, you observe that some of these balls are not round. You analyze the problem and find that it can be prevented by making some changes to the procedures. Therefore, you make changes to the procedure to prevent this problem again. This is an example of:

  1. Corrective action
  2. Preventive action
  3. Correction
  4. Defect repair
Correct Answer

Q10. The Make-or-Buy analysis is a technique used as part of the Plan Procurement Management process. It can determine whether the project team can produce a particular product or service, or if it should be purchased. The analysis to arrive at a decision should include:

  1. Indirect costs only
  2. Direct as well as Indirect costs
  3. Direct costs only
  4. Staffing costs only
Correct Answer










User Agreement| |Privacy Policy