IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

All requested changes to a contract go through Contract Change Control Systems of both parties. The Contract Change Control system documents all requested changes for future reference. However, requested but unresolved changes might not make it up to either party’s Change Control Systems. If you are contesting a dispute, where can you find a record of such requested changes?
  1. Procurement management plan
  2. Project management plan
  3. Project correspondence
  4. Approved change requests log






Q2. A project manager is using a Risk Diagramming technique that is a graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes. This would be:

  1. A system flow chart
  2. An Influence Diagram
  3. A Pareto chart
  4. Histogram
Correct Answer

Q3. In planning your project, which would generally have the highest priority; quality, cost, or schedule?

  1. Cost is most important, quality next, and then schedule
  2. Quality is more important than cost or schedule
  3. Schedule is most important, quality next, and then cost
  4. It should be decided for each project.
Correct Answer

Q4. An obstacle to team building in a matrix organization is that the:

  1. Team organization is technically focused
  2. Team members are borrowed resources and can be hard to motivate.
  3. Teams are too centralized
  4. Teams are too large and therefore very hard to handle.
Correct Answer

Q5. What is the name of the process required to ensure timely and appropriate generation, collection, dissemination, and disposal of project information?

  1. Quality management
  2. Communications management
  3. Procurement management
  4. Scope management
Correct Answer

Q6. You have been managing a construction project in a developing country, and now you are closing the project. The tools and equipment that were used on the project have to be returned to your company’s European headquarters. A nongovernmental organization that builds and repairs medical facilities in this country has come to you to request that this equipment be donated to them. What should you do?

  1. Donate all tools and equipment
  2. Refuse the request
  3. Donate only the tools and equipment whose value is below your purchase approval limit
  4. Notify the appropriate management
Correct Answer

Q7. A team member determines that the scope for her activity is no longer valid. She comes to you for advice on making the change. To which of the following documents should the project manager refer to make this change?

  1. The project management information system
  2. The scope management plan
  3. The cost management plan
  4. The work authorization system
Correct Answer

Q8. A project manager has assembled the project team, identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions, and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?

  1. Simulation
  2. Risk mitigation
  3. Overall risk ranking for the project
  4. Involvement of other stakeholders
Correct Answer

Q9. Who determines the project scope requirements of a new project?

  1. The customer
  2. The stakeholders
  3. The project manager
  4. Senior management
Correct Answer

Q10. Which of the following MUST be an agenda item at all team meetings?

  1. Discussion of project risks
  2. Status of current activities
  3. Identification of new activities
  4. Review of project problems.
Correct Answer










User Agreement| |Privacy Policy