IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Your company puts a new product into the marketplace without any reports of problems. However, your internal research indicates that there is a possibility of serious injuries that would cost $20,000,000 to fix. What should you do?
  1. Make the necessary modifications to the products in production
  2. Recall all the existing product
  3. Wait until an injury to verify the impact
  4. Obtain insurance to cover the anticipated damages






Q2. A project has just begun when one of the stakeholders asks the project manager about making a change to the format of the deliverable for activity Y. She wants to know how to go about submitting the change for review. The project manager should direct her to:

  1. The change control board
  2. The communications management plan.
  3. The sponsor
  4. The change control system
Correct Answer

Q3. The project manager has had some difficulty in getting the team to complete work efforts but he feels that the changes he made to the reward system will fix the problem. The number of stakeholders on the project has grown by 20 percent and the number of activities being completed late is growing. The project manager has heard from management that the project might become a higher priority if their competition comes out with a new product that uses wireless technology. Based on this, it would be BEST for the project manager to:

  1. Re-estimate the activities and prepare to create a new schedule
  2. Perform configuration management
  3. Recreate the project work authorization system
  4. Better respond to risk event triggers 30
Correct Answer

Q4. In an IT project, after several brainstorming sessions with customers, Kurt established various project deliverables. Two weeks later, while reviewing the plan, Kurt identifies two similar deliverables and decides to merge them into a single deliverable. What should Kurt do next?

  1. Merge the deliverables and inform the customer
  2. Submit the need to merge to the customer
  3. Merge the deliverables but do not inform the customer
  4. Merge the deliverables but do not update the project management plan
Correct Answer

Q5. A customer has given you a procurement of work for a complex, eightmonth project that has a few unknowns. The customer has asked you to just “get it done” and only wants to see you at the end of eight months when you deliver the finished project. Under these circumstances, which of the following is the BEST thing to do?

  1. Complete the project as requested, but verify its scope with the customer occasionally throughout.
  2. Complete the project within eight months without contacting the customer during this time.
  3. Ask management to check in with the customer occasionally.
  4. Complete the project, but document that the customer did not want contact.
Correct Answer

Q6. Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. With the limited detail available to her, what would you expect the range of her estimate to be, and what would you call such an estimate?

  1. -25 to +25%, Absolute Cost
  2. -5 to +10%, Narrow
  3. -1 to +1%, Definitive
  4. -25 to +75%, Rough Order of Magnitude
Correct Answer

Q7. Which of the following is the correct sequence of the PMBOK processes that collects work performance data, converts it to work performance information, formats it into work performance reports, and distributes these reports?

  1. Direct & Manage Project Work -> Monitor & Control Project Work -> Monitor Communications -> Manage Communications
  2. Monitor Communications -> Direct & Manage Project Work -> Monitor & Control Project Work -> Manage Communications
  3. Direct & Manage Project Work -> Monitor Communications -> Monitor & Control Project Work -> Manage Communications
  4. Direct & Manage Project Work -> Monitor & Control Project Work -> Manage Communications -> Monitor Communications
Correct Answer

Q8. During a discussion with the quality department, Dave, a project manager, was told that as applied to projects, the terms “prevention” and “inspection” are synonymous. However, his understanding of the terms is different. What would you comment on this situation?

  1. The project manager is correct. Prevention is about keeping errors out of the process; inspection is about keeping errors out of the customer’s hands.
  2. The project manager is correct. Inspection is about keeping errors out of the process; prevention is about keeping errors out of the customer’s hands.
  3. The project manager is wrong. Both inspection and prevention are about keeping errors out of the customer’s hands. They are used in different contexts.
  4. The project manager is wrong. Both inspection and prevention are about keeping errors out of the process. They are used in different contexts.
Correct Answer

Q9. Key project stakeholders can significantly influence a project in many ways. During which stage of the project do these stakeholders have the maximum ability to influence a project?

  1. Planning
  2. Initiating
  3. Executing
  4. Monitoring & Controlling
Correct Answer

Q10. Which of the following is CORRECT?

  1. The critical path helps prove how long the project will take
  2. There can be only one critical path
  3. The network diagram will change every time the end date changes
  4. A project can never have negative float.
Correct Answer










User Agreement| |Privacy Policy