IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labour hours per installation from past projects to predict the future. This is an example of which of the following?
  1. Parametric estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Monte Carlo analysis 48






Q2. You have found you do not yet have an accurate estimate of the number and skill levels of resources needed for the scheduled activity Build Racks for Data Center. You need this estimate for presentation to your Human Resources department later in the week. You have decided to decompose the Build Racks for Data Center activity into smaller components such as take equipment out of box, review equipment for completeness, build frame, and install rails. Then you plan to estimate the resources for each smaller component and combine those estimates into an aggregate. This is an example of:

  1. Aggregate Estimating
  2. Alternative Analysis
  3. Bottom-up Estimating
  4. Rolling Wave Estimating
Correct Answer

Q3. In general, Perform Qualitative Risk Analysis is:

  1. Not often completed
  2. Complete and 100 percent accurate
  3. In-depth and thorough
  4. focused on high-priority risks
Correct Answer

Q4. A project manager for a small construction company has a project hat was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US 90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?

  1. Project manager
  2. Senior management
  3. Project sponsor
  4. Manager of the project management office
Correct Answer

Q5. Lag means:

  1. The amount of time an activity can be delayed without delaying the project finish date
  2. The amount of time an activity can be delayed without delaying the early start date of its successor.
  3. Waiting time
  4. The product of a forward and backward pass
Correct Answer

Q6. A project manager calls you in as a consultant to provide input on developing the Project Charter. According to the PMBOK, your contribution to the project could best be termed as:

  1. Professional Consultant
  2. Expert Judgment
  3. Charter Consultant
  4. Expert Consultancy
Correct Answer

Q7. A control chart should always contain:

  1. Upper and lower warning limits
  2. The moving average
  3. Upper and lower control limits
  4. Upper and lower specification limits
Correct Answer

Q8. Which of the following is NOT used in initiating a project?

  1. Project statement of work.
  2. The contract.
  3. Enterprise environmental factors.
  4. Earned value analysis.
Correct Answer

Q9. What conflict resolution technique is a project manager using when he says, “I cannot deal with this issue now!”

  1. Problem solving
  2. Forcing
  3. Withdrawal
  4. Compromising.
Correct Answer

Q10. Though you have tried to plan the project to accommodate all major contingencies, you are now asked for the fifth time to decrease the length of time the project will take to complete. The person completing activity C is no longer talking to you because of the added work she needed to do to accommodate previous decrease in time. She has already told you she cannot shorten her activity any more. The person doing activity D has been replaced by a new and less tested resource. The risk of crashing activity F is small. Based on this and the chart, what is the BEST thing to do?

  1. Determine why there have been so many decreases to the project length
  2. Invite the person doing activity C to lunch to talk about her problems
  3. Evaluate the risk added to the project with the change of resources on activity D
  4. Make changes to the project to decrease the time the project will take.
Correct Answer










User Agreement| |Privacy Policy