IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a _______ for the second half of the project?
  1. Work breakdown structure
  2. Resource histogram
  3. Staffing management plan
  4. Responsibility assigned matrix.






Q2. All of the following are parts of the Direct and Manage Project Work process EXCEPT:

  1. Identifying changes
  2. Using a work breakdown structure
  3. Implementing corrective actions
  4. Setting up a project control system 3
Correct Answer

Q3. The sponsor has asked you to require that each piece of the project scope be planned, estimated, and scheduled. The sponsor also wants to authorize each piece of the project management plan after the documentation is assembled. What is the MOST appropriate response to these requests?

  1. Politely advise the sponsor to forego the authorization of work.
  2. Provide the sponsor with a schedule of when the components will be ready for authorization
  3. Ask the sponsor to authorize each piece before it is completed
  4. Tell the sponsor that the chance for authorization will come after the pieces of the project management plan are compiled
Correct Answer

Q4. The project management team performed activities such as measuring, examining, and verifying to determine whether work and deliverables met requirements and product acceptance criteria. Which of the following choices refers to a different set of activities than the ones just mentioned?

  1. Walkthroughs
  2. Prevention
  3. Inspection
  4. Reviews
Correct Answer

Q5. While reviewing project procurement and accounting records for your project, you discover there is a pattern of unauthorized expenses by a specific resource. These expenses are not within the scope of the project and were somewhat camouflaged within a number of large and complicated expense reports. What do you do?

  1. If the total expenses are less than 1 percent of the project budget, do nothing
  2. Fire the resource
  3. Notify the appropriate management immediately
  4. Confront the resource
Correct Answer

Q6. Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

  1. It would increase the critical path
  2. Communication would be more complex
  3. There would be no effect
  4. It would delay activity F
Correct Answer

Q7. Gene is the project manager of a large highway expansion project. He has a number of stakeholders with competing priorities and agendas, and he often has to resolve conflicts among stakeholders. Which knowledge area manages communications with the project stakeholders?

  1. Project Quality Management
  2. Project Stakeholder Management
  3. Project Communications Management
  4. Project Resource Management
Correct Answer

Q8. In the earned value management technique, the cost performance baseline is:

  1. Cost Measurement Baseline (CMB)
  2. Performance Measurement Baseline (PMB)
  3. Performance Base Value (PBV)
  4. Actual Baseline (AB)
Correct Answer

Q9. Nancy’s project is 80 percent complete. Which of the following project documents is least likely to be updated during the Monitor Stakeholder Engagement process performed at this stage?

  1. Project charter
  2. Risk register
  3. Stakeholder register
  4. Issue log
Correct Answer

Q10. By policy, the project management office regularly evaluates project performance. This is done in order to ensure standards are being followed. This is an example of:

  1. Plan Quality
  2. Manage Quality
  3. Control Quality
  4. Quality Management
Correct Answer










User Agreement| |Privacy Policy