IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following contains an item that is NOT an output of the Plan Procurements process?
  1. Procurement management plan, procurement documents, procurement contract award
  2. Procurement statement of work, procurement management plan, make-or-buy decisions
  3. Requested changes, procurement management plan, source selection criteria
  4. Make-or-buy decisions, procurement statement of work, change requests.






Q2. The project is not going well and many changes are being made. Which of the following should you do FIRST to gain control of the project?

  1. Review the project scope with the stakeholders
  2. Create a new change form
  3. Remind everyone of the change procedures
  4. Ask the sponsor to review the project charter
Correct Answer

Q3. You are managing a project for your company constructing an office complex in another country. The construction work on two of the buildings is complete, and those buildings are ready for move-in. However, the construction supervisor informs you that you must pay a fee to a local government agency to issue an occupancy permit for any new construction in that country. What should you do?

  1. Pay the fee
  2. Ask your legal department if this is legal
  3. Notify project stakeholders that you have been asked to pay a bribe
  4. Do not pay the fee
Correct Answer

Q4. Which of the following actions decreases the risk of the project failing to meet its goals and objectives?

  1. Discouraging changes to the initial project scope
  2. Acquiring more than required resources
  3. Active management of stakeholders
  4. Fast-tacking the project schedule to finish the project before deadline
Correct Answer

Q5. A scope change is made on the project. You have determined the effect on the schedule, performed integrated change control, and adjusted the project baselines and the project management plan. What is the NEXT thing to do?

  1. Look for impacts to cost
  2. Notify stakeholders affected by the change.
  3. Submit the change to the change control board for approval
  4. Change the work breakdown structure.
Correct Answer

Q6. During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources?

  1. The project manager
  2. The functional manager
  3. The team
  4. The project sponsor.
Correct Answer

Q7. A project manager wants to use a group decision-making technique to generate, classify and prioritize requirements. Which of these is not a valid group decision-making technique?

  1. Plurality
  2. Singularity
  3. Majority
  4. Unanimity
Correct Answer

Q8. Which of the following helps the project team to look at many sources from which project risks may arise in a risk identification exercise?

  1. Work Breakdown Structure
  2. Risk Breakdown Structure
  3. Risk register
  4. Issue log
Correct Answer

Q9. Analysis of the scope performance resulted in a change request to the scope baseline. Change requests can include all the following except:

  1. Defect repair
  2. Supportive action
  3. Corrective action
  4. Preventive action
Correct Answer

Q10. Which of the following is not an input to the Develop Project Charter process?

  1. Agreements
  2. Business Case
  3. Benefits management plan
  4. Stakeholder register
Correct Answer










User Agreement| |Privacy Policy