IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following actions decreases the risk of the project failing to meet its goals and objectives?
  1. Discouraging changes to the initial project scope
  2. Acquiring more than required resources
  3. Active management of stakeholders
  4. Fast-tacking the project schedule to finish the project before deadline






Q2. Earned value measurement is an example of:

  1. Performance reporting
  2. Planning control
  3. Ishikawa diagrams
  4. Integrating the project components into a whole.
Correct Answer

Q3. You are responsible for IT maintenance in your organization. The head of the IT department comes to you with an internet security expert and tells you to disable auto login and force authentic login based on a new password. The password will be 15 characters long and consist of letters, numerals, and one special character, and this password must expire after every 30 days. This is an example of:

  1. Operation
  2. Project
  3. Maintenance
  4. None of the above
Correct Answer

Q4. The preparation of the scope baseline can BEST be described as involving:

  1. The functional managers
  2. The project team
  3. All the stakeholders
  4. The project expediter.
Correct Answer

Q5. Which motivational theory says that working conditions, salary, and relationships at work do NOT improve motivation?

  1. Maslow
  2. Deming
  3. McGregor
  4. Herzberg
Correct Answer

Q6. Three items from the issue log have been assigned to a team member. However, no action has been taken by the agreed-upon due date. After three calls to the team member, the work is finally completed. Which of the following is the BEST preventive action to take NOW?

  1. Remove the team member from the team if possible
  2. Meet with the team member to uncover the reasons why there were problems
  3. Make sure the action item list is distributed to all the right parties
  4. Make sure items assigned in the action item list are accepted by the team members they are assigned to.
Correct Answer

Q7. On any project, the configuration control should be focused on the specification of:

  1. Deliverables and processes
  2. Scope and cost
  3. Risk and resources
  4. Schedule and quality
Correct Answer

Q8. The technique of comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance is known as:

  1. Workbench
  2. Benchmarking
  3. Quality control
  4. Dependency
Correct Answer

Q9. A project has gone out of control, and the project manager is trying to bring it back under control. There have been a number of changes to the project scope. Some of these changes resulted in further changes, causing project cost to spiral upward and causing the project to go out of schedule. This is known as:

  1. Scope creep
  2. Scope jump
  3. Project creep
  4. Scope control
Correct Answer

Q10. In your project, two important stakeholders are having some issues. To keep this issue from escalating further you intervene and resolve the issue. After the issue is resolved you asked your team member to record the issue so in the future a lesson can be learned from it. Where will you note the issues between stakeholders?

  1. Risk register
  2. Issue log
  3. Stakeholder register
  4. Change log
Correct Answer










User Agreement| |Privacy Policy