IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

On any project, the configuration control should be focused on the specification of:
  1. Deliverables and processes
  2. Scope and cost
  3. Risk and resources
  4. Schedule and quality






Q2. Which of the following is an output of the Define Activities process?

  1. A WBS
  2. An activity list
  3. A network diagram
  4. A project schedule
Correct Answer

Q3. Which of the following does NOT assess the value a project brings to an organization?

  1. Benefit cost analysis
  2. Net present value
  3. Value analysis
  4. Needs assessment
Correct Answer

Q4. You have finished the Plan Risk Responses process and are left with residual risks. What should you do with them?

  1. Document them in the risk register and revisit them during project executing
  2. Deal with them as they arise during project executing
  3. Include them as part of the contingency plans
  4. Perform a sensitivity analysis on them.
Correct Answer

Q5. Which of the following is an advantage of centralized contracting?

  1. Increased expertise
  2. Easier access
  3. No home
  4. More loyalty to the project.
Correct Answer

Q6. In quality terms, one of the meanings of “out of control” is:

  1. Someone on the team is upset
  2. A data point on a control chart falls inside the upper or lower control limit.
  3. Several data points on the same side of the mean within the upper and lower control limits.
  4. A data point is within 1 sigma.
Correct Answer

Q7. Value analysis is performed to get:

  1. More value from the cost analysis.
  2. Management to buy into the project
  3. The team to buy into the project.
  4. A less costly way of doing the same work.
Correct Answer

Q8. Skills such as empathy, influence, creativity, and group encouragement are valuable assets when managing the project team. These skills are often referred to as ______________.

  1. Effort-based management
  2. Feedback-based skills
  3. Ad hoc skills
  4. Soft skills
Correct Answer

Q9. You are managing two projects. The first project is to design a simulator for a client which he will use in his driving school. The second project is to install a security system on a client’s premises to ensure its security around the clock. What is your role here?

  1. Project manager
  2. Portfolio manager
  3. Program manager
  4. Project coordinator
Correct Answer

Q10. You have a project with a budget of 100,000 USD. The duration of the project is 20 months, and the work is evenly distributed throughout the duration. After 10 months, you review the project’s progress and you find that 55% of the work is completed and 65,000 USD has been spent. Based on the above information, you come to the conclusion that:

  1. The project is behind schedule
  2. The project is ahead of schedule
  3. The project is under budget
  4. Not enough information
Correct Answer










User Agreement| |Privacy Policy