Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

The term Progressive Elaboration incorrectly represents which of the following?
  1. Changes to project scope
  2. Rolling wave planning
  3. Detailing out the product requirements developed during the initiation process.
  4. Production of fabrication and construction drawings from the design drawings for a chemical plant.






Q2. A project has gone out of control, and the project manager is trying to bring it back under control. There have been a number of changes to the project scope. Some of these changes resulted in further changes, causing project cost to spiral upward and causing the project to go out of schedule. This is known as:

  1. Scope creep
  2. Scope jump
  3. Project creep
  4. Scope control
Correct Answer

Q3. A new project manager has been hired in your company, and you have been asked to mentor her. Because she is well trained, she is planning her project in great detail. Her first project for the company is relatively low priority, and you feel that the project manager is planning too many project control meetings. Which of the following would be the BEST thing to tell her?

  1. Strike a balance between the extent of the control system and the risk of unfavorable project outcomes.
  2. Make sure you identify more than 40 risks, and then have more than one meeting a month
  3. A good project management plan should be about90 percent complete before starting work
  4. Make sure you include milestones to help plan the project charter.
Correct Answer

Q4. A project manager works in a company that has a matrix organizational structure. A server administrator is assigned to the project manager’s project team. The server administrator is not taking direction from the project manager and the delay in the server administrator’s activities is causing a negative variance to the schedule. The server administrator works for the director of server administration. Who is primarily responsible for solving this problem?

  1. The project manager
  2. The server administrator
  3. The director of server administration
  4. The sponsor
Correct Answer

Q5. A project manager has to resolve two problems. Both problems can occur in a single trial. In this situation, what is the BEST action the project manager can take?

  1. Develop a solution for each problem.
  2. Develop a solution that solves both problems.
  3. Use a statistically independent trial
  4. No solution is needed; the two problems cancel each other out.
Correct Answer

Q6. The engineering department has uncovered a problem with the cost accounting system and has asked the systems department to analyze what is wrong and fix the problem. You are a project manager working with the cost accounting programs on another project. Management has issued a change request to the change control board to add the new work to your project. Your existing project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 1.3 so you have some room to ad work without delaying your existing project. After some analysis, you determine that the new work and existing work do not overlap and can be done concurrently. They also require different skill sets. Which of the following is the BEST thing to do?

  1. Develop Project Charter
  2. Re-estimate the project schedule with input from the engineering department
  3. Verify the scope of the new work with the help of the stakeholders
  4. Identify specific changes to the existing work.
Correct Answer

Q7. Your company is way behind schedule in the deployment of a government-mandated change to a health care processing system that must be in production by the end of the year. To meet the due date, you and your team have met and decided to hire an additional 50 programmers to work with the existing staff. This is an example of what?

  1. Resource Leveling
  2. Fast Tracking
  3. Crashing
  4. Risk Transference
Correct Answer

Q8. You have been given a multi-year project to build a refinery. This is a very large and complex project, and you now need to estimate the cost for this project. What basic assumption will you need to make while estimating the cost for this project?

  1. If you get the project budget in phases
  2. You will be given all costs and resources at the beginning of the project
  3. Whether the estimate will be limited to direct costs or if it will include the indirect costs as well
  4. If the project schedule is fixed or based on events
Correct Answer

Q9. The six-month project has 300 work packages and a US $600,000 budget. Three months into the project 150 work packages are complete and US $300,000 has been spent. Which of the following is CORRECT?

  1. The project is on time and on budget
  2. The project manager should reevaluate cost performance but not worry about time.
  3. The project needs 50 more work packages to be completed to be on time.
  4. There is not enough information
Correct Answer

Q10. The project has been going well when one of the suppliers informs you that, as they warned you during project planning, they will deliver your equipment two days late. At the same time, you get a call from a team member informing you that the critical path activity she is working on will take longer to complete than planned. What is the BEST thing to do?

  1. Use a contingency reserve for the first, and find out how much later the activity will be
  2. Ask for a change order for each
  3. Have both reviewed with the change control board
  4. Find out why the activity was late 8
Correct Answer