IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A project is ending one of its phases. What should be done before moving on to the next phase?
  1. Team meeting
  2. Validate Scope
  3. Management meeting
  4. Scope management 05






Q2. Which of the following should be avoided while applying logical relationships to project activities:

  1. Applying the SS relationship with a lead
  2. Applying the SS relationship with a lag
  3. Applying the SF relationship
  4. Applying multiple relationships between the same activities
Correct Answer

Q3. Which of the following defines things the project manager needs to do regarding cost?

  1. Never just accept constraints from management, periodically recalculate the estimate to complete, meet any agreed-upon estimates
  2. Meet any agreed-upon estimates, estimate larger-sized work components, accept constraints from management
  3. Periodically recalculate the estimate to complete, increase estimates by eliminating risks, re-estimate when changes are requested
  4. Never recalculate the estimate to complete, never just accept constraints from management, and only use historical records for accurate estimates.
Correct Answer

Q4. Design of experiments:

  1. Identifies which variables have the most influence on a quality outcome
  2. Identifies which variables have the least influence on a quality outcome
  3. Determines what a quality outcome is
  4. Determines the methods to be used for research and development.
Correct Answer

Q5. Your organization gets a new project and wants you to assign the project manager for this project. As management is busy with other activities, they ask you to develop the project charter so the project can get started. To develop the project charter, which of the following is not needed?

  1. Strategic plan
  2. Business case
  3. Agreements
  4. Project plan
Correct Answer

Q6. The project manager’s role during the executing process group of the project can BEST be described as:

  1. A Director
  2. An Integrator
  3. A Coordinator
  4. A Leader
Correct Answer

Q7. A project manager completed the work package estimating process and then performed a Monte Carlo analysis to determine the amount of risk reserve needed on the project. Why is this incorrect?

  1. The risks per work package have not been identified
  2. The critical path was not calculated
  3. The network diagram was not used
  4. The schedule was not developed.
Correct Answer

Q8. When is it MOST important that integration is performed?

  1. During project planning
  2. During project executing
  3. At key interface points
  4. At the end of each project management process
Correct Answer

Q9. Risks may be identified during the entire lifecycle of a project. Identify Risks is what type of process?

  1. Qualitative
  2. Effort-driven
  3. Discrete
  4. Iterative
Correct Answer

Q10. Project risks should be identified by:

  1. Those invited to the risk identification process only
  2. Key project stakeholders only
  3. The project manager only
  4. All project personnel
Correct Answer










User Agreement| |Privacy Policy