IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following should be avoided while applying logical relationships to project activities:
  1. Applying the SS relationship with a lead
  2. Applying the SS relationship with a lag
  3. Applying the SF relationship
  4. Applying multiple relationships between the same activities






Q2. What do the buyer and seller have in common with regard to Control Procurements?

  1. Both parties ensure that they meet their contractual obligations and that their own legal rights are protected.
  2. Both parties have specific resources that can be idle.
  3. Both parties have a contract change management plan.
  4. Each party has its own project plan and legal team.
Correct Answer

Q3. A decision tree is a Perform Quantitative Risk Analysis technique. A decision tree is represented by a Decision Tree Diagram. The decision tree describes a situation under consideration, the implications of each of the available choices, and the possible scenarios. A Decision Tree Diagram shows how to make a decision among alternative capital strategies known as:

  1. Alternative nodes
  2. Question points
  3. Decision nodes
  4. Checkpoints
Correct Answer

Q4. If planned value (PV) is US $29,000, actual cost (AC) is US $32,000, and earned value (EV) is US $30,000, what is the schedule variance (SV)?

  1. 0.938
  2. $1,000
  3. 1.034
  4. ($2,000) 19
Correct Answer

Q5. Which of the following tools helps you to determine whether the subcontractor’s work is meeting the quality requirements?

  1. Quality control
  2. Quality audit
  3. Inspection of deliverables
  4. Delphi technique
Correct Answer

Q6. An e-mail is forwarded to you highlighting conflict between two team members. Which conflict resolution technique would you use?

  1. Forcing
  2. Compromising
  3. Avoiding
  4. Confronting
Correct Answer

Q7. An estimate that is +/-50 percent of actual is considered a:

  1. Budget estimate
  2. Rough order of magnitude estimate
  3. Definitive estimate
  4. Parametric estimate.
Correct Answer

Q8. A project manager had a complex problem o solve and made a decision about what needed to be done. A few months later, the problem resurfaced. What did the project manager MOST likely not do?

  1. Proper risk analysis
  2. Confirm that the decision solved the problem
  3. Have the project sponsor validate the decision
  4. Use an Ishikawa diagram.
Correct Answer

Q9. You have just been assigned as project manager for a large telecommunications project. This one-year project is about halfway done. The project team consists of five sellers and 20 of your company’s employees. You want to understand who is responsible for doing what on the project. Where would you find such information?

  1. Responsibility assignment matrix
  2. Resource histogram
  3. Bar chart
  4. Project organization chart.
Correct Answer

Q10. To create a quality product, the project management team invested in training the project team members and purchasing high-end equipment. Such costs are:

  1. Failure costs
  2. Costs of Nonconformance
  3. Appraisal costs
  4. Prevention costs
Correct Answer










User Agreement| |Privacy Policy