The products manufactured during 1800s were unique. How quality was ensured in this era?
  1. Through renovation
  2. Through inspection
  3. Through calculation
  4. Through repair






Q2. An unbiased dice is rolled once. The probability of getting a number greater than 4 is:

  1. ¼
  2. 1/6
  3. ½
  4. 1/3
Correct Answer

Q3. Validation of root cause is made only when which standard(s) is met:

  1. There is a statistically significant relationship between the suspected root cause and the effect.
  2. The data is normal
  3. Knowledge of the process corroborates this causal relationship.
  4. Both A and C above
Correct Answer

Q4. Juran's Quality trilogy emphasizes the roles of quality planning, quality control and ______________

  1. Quality Definition
  2. Quality enhancement
  3. Quality improvement
  4. quality maintenance
Correct Answer

Q5. Which of the following is not a target of Total Quality Management:

  1. Customer Satisfaction
  2. Reducing manpower
  3. Continuous Cost Reduction
  4. Continuous Operational Improvement
Correct Answer

Q6. At the time of making a purchase agreement with a vendor, what is important to mention about inspection?

  1. the characteristics of the product that are to be inspected
  2. the tolerances that would be allowed
  3. the reputation of the vendor
  4. a & b both (not sure)
Correct Answer

Q7. Statistical Process Control is used in quality programs to determine whether repetitive operations meet predictable standards. The process uses ______________ to permit accurate monitoring of the operation.

  1. 100 percent inspection and random rejection
  2. acceptance sampling and automatic rejection
  3. continuous sampling and error detection methods
  4. random sampling and corrective procedures
  5. statistical sampling and control procedures
Correct Answer

Q8. A result is called "statistically significant" whenever

  1. The null hypothesis is true.
  2. The alternative hypothesis is true.
  3. The p-value is less or equal to the significance level.
  4. The p-value is larger than the significance level.
Correct Answer

Q9. The ______________ sum of squares measures the variability of the observed values around their respective treatment means.

  1. treatment
  2. error
  3. interaction
  4. total
Correct Answer

Q10. The primary components of quality management are quality ______________.

  1. insurance, assurance, and warranty
  2. inspections, certifications, and validations
  3. philosophy, assurance, and control
  4. form, fit, and function
  5. reliability, maintainability, and availability
Correct Answer