Gordon is currently developing his project‘s stakeholder engagement strategy. All enterprise environmental factors should be considered during this process. Which of the following enterprise environmental factors should receive particular attention during this process?
  1. Project templates
  2. Lessons learned from past similar projects
  3. Commercial databases
  4. The organization‘s culture and political climate






Q2. Which of the following processes will determine the correctness of deliverables?

  1. Plan Deliverables
  2. Plan Quality Management
  3. Control Quality
  4. Manage Quality
Correct Answer

Q3. A software development project team has determined that the best way to mitigate the risk of not having the computational resources to complete all bug testing on schedule is to add three more servers to the test bed. However, the network may not have enough capacity to handle the extra load of those three servers and could fail. This type of risk is a _______________ risk.

  1. Secondary
  2. Simulation
  3. Bottleneck
  4. Hidden
Correct Answer

Q4. Which of the following is a tool or technique of the Manage Stakeholder Engagement process?

  1. Communication technology
  2. Communication models
  3. Communication standard
  4. Communication skills
Correct Answer

Q5. A project manager has a project with a team member’s performance. What is the BEST form of communication for addressing this problem?

  1. Formal written communication
  2. Formal verbal communication
  3. Informal written communication
  4. Informal verbal communication
Correct Answer

Q6. Which of the following is NOT an output of the Manage Stakeholders process?

  1. Approved corrective actions
  2. Deliverables
  3. Updates to the project management plan
  4. Organizational process asset updates 46
Correct Answer

Q7. A project manager is assigned to a new, high priority project. There are only five available resources because other resources are already committed to projects. The time available to complete the project is less than half the time needed, and the project manager cannot convince management to change the end date. The project manager should:

  1. Coordinate with team members the overtime necessary to complete the work
  2. Provide the team with opportunities to produce acceptable quality on the work that can be accomplished
  3. Look for any scope that can be cut from the project.
  4. Use more experienced resources to complete the work faster.
Correct Answer

Q8. You have been hired as a consultant for a project that is in trouble. You meet the project manager and ask several questions regarding the project budget, the project end date, etc. The project manager was not able to answer some of these questions properly, so you decided to verify them yourself. What document will you refer to in order to verify such facts?

  1. Project management plan
  2. Cost and schedule baselines
  3. Project charter
  4. Performance report
Correct Answer

Q9. You are meeting with your stakeholders to gather requirements for your project. You are well aware that requirements to be gathered include both product and project requirements. All the following tools can be used to gather, define, and analyze project requirements from stakeholders except:

  1. Surveys
  2. Focus Groups
  3. Decomposition
  4. Prototypes
Correct Answer

Q10. You are the project level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

  1. Quality audits
  2. Risk quantification reports
  3. Regression analysis
  4. Monte Carlo analysis
Correct Answer