IRGST

Home Question Bank Online Exams Articles GK Products & Services In Mirrors About Contact Sign in/up

IRGST Question Bank for Exam Preparation

Select Knowledge area and click the cube

Generate random question

Question:

During the project execution, some people stole your consumables. You did not identify this threat earlier, though you were able to manage the situation through a workaround. This risk did not have much of an impact on your cost baseline but the schedule was impacted. Management is aware of the issue and to get the complete picture they insist you provide them the performance report. Which of the following information will you provide to them?
  • Status of deliverables
  • Actual cost, actual duration, etc.
  • Milestones status
  • Memos