Question:

You have received an urgent call from management and they asked you to find the cost estimate of a new project. Since time is critical and you have to provide them with the cost estimate, which technique will you use to calculate the project cost?
  • Parametric
  • Analogous
  • Bottom up
  • Symmetric estimate