Question:

You have joined a new organization and are assigned a project. This is a new type of project but the organization has completed many similar projects in the past. You decide to review the lessons learned from past projects. You go to the archives and ask for the lessons learned from past projects. Lessons learned is a part of which of the following?
  • Organizational process assets
  • Enterprise environment factor
  • Project management plan
  • Project archive