Question:

Your project is delayed because of some regulatory issues and the client has asked you to stop the work until he gets government clearance. The project team members are afraid that the project may be terminated early and you may need to enter into the close project process. In which of the following cases will you not perform the close project or close phase process?
  • When the project is terminated due to cost overrun
  • When the project is terminated due to schedule overrun
  • The client decided to terminate the project
  • None of the above