Question:

During the planning phase, you have created the WBS for the work that you are about to complete. However, because of a lack of information you are not able to create the WBS for the rest of the work, so you leave it until you get the correct and detailed information. This is an example of:
  • Progressive elaboration
  • Improper collecting requirement process
  • Rolling wave planning
  • Improper scope statement