IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Quality Question Bank
for Exam preparation

Select Knowledge area

Question:

The main purpose of the analyze phase is to:
  1. Identify possible solutions
  2. Create a pilot plan
  3. Identify and validate root causes
  4. All of the above






Q2. Machine wear and tear is ______________ source of variation.

  1. Random
  2. Natural
  3. Assignable
  4. Cannot be determined
Correct Answer

Q3. establishing measurements based on customer needs for optimizing product design is known as ______________

  1. Quality design
  2. quality improvement
  3. quality control
  4. Quality planning
Correct Answer

Q4. Identify the cost not likely to reduce as a result of better quality.

  1. Maintenance costs
  2. Inspection costs
  3. Scrap costs
  4. Warranty and service costs
Correct Answer

Q5. The x bar chart monitors:

  1. Between sample variability
  2. Within sample variability
  3. Instantaneous variability
  4. Natural variability
Correct Answer

Q6. Average Total Inspection is defined as:

  1. Average of rejected lots and accepted lots
  2. Average number of units inspected per lot
  3. Average of rejected Lots
  4. Average of accepted Lots
Correct Answer

Q7. Suppose box A contains 4 red and 5 blue coins and box B contains 6 red and 3 blue coins. A coin is chosen at random from the box A and placed in box B. Finally, a coin is chosen at random from among those now in box B. What is the probability a blue coin was transferred from box A to box B given that the coin chosen from box B is red?

  1. 15/29
  2. 14/29
  3. 1/2
  4. 7/10
Correct Answer

Q8. The concept that it is easier and less costly to do the work right the first time is called:

  1. Zero defects
  2. Continuous improvement
  3. DTRTRTFT
  4. The customer is the next person in the process
Correct Answer

Q9. X bar should never be interpreted when:

  1. R chart shows out of control points
  2. X bar chart shows out of control points
  3. The process mean is not known
  4. None of the above
Correct Answer

Q10. Four basic characteristics of an optimal process are:

  1. Economy, efficiency, control, quality
  2. Quality, Improvement, efficiency, productivity
  3. Economy, efficiency, productivity, cost
  4. Economy, efficiency, productivity, quality
Correct Answer










User Agreement| |Privacy Policy