IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following BEST describes the difference between the Control Scope process and Perform Integrated Change Control?
  1. Control Scope focuses on making changes to the product scope and Perform Integrated Change Control focuses on making changes to integration.
  2. Control Scope focuses on controlling the scope of the project and Perform Integrated Change Control focuses on determining the impact of a change of scope on time, cost, quality, risk, resources, and customer satisfaction
  3. Control Scope focuses on controlling the scope of the project and Perform Integrated Change Control focuses on making changes to integration
  4. Control Scope focuses on making changes to the product scope and Perform Integrated Change Control focuses on determining the impact of a change to scope, time, cost, quality, resources, and customer satisfaction.






Q2. Your manager is presenting a status report of all projects being run in his division. He reports that all projects are showing a positive CV. However, you know that your status reports for the last several weeks have been reporting a negative CV. What do you do?

  1. Do nothing.
  2. Offer to review all your manager's combined status reports before he presents them.
  3. Notify the appropriate management immediately.
  4. Ask your manager if that information was simply a typographical error.
Correct Answer

Q3. What percent of time do project managers spend communicating?

  1. 90%
  2. 20%
  3. 70%
  4. 25%
Correct Answer

Q4. Which of the following processes deals with maintaining the integrity of baselines by releasing only approved changes for incorporation into the project management plan?

  1. Perform Integrated Change Control
  2. Direct and Manage Project Work
  3. Develop Project Management Plan
  4. Monitor and Control Project Work
Correct Answer

Q5. The six-month project has 300 work packages and a US $600,000 budget. Three months into the project 150 work packages are complete and US $300,000 has been spent. Which of the following is CORRECT?

  1. The project is on time and on budget
  2. The project manager should reevaluate cost performance but not worry about time.
  3. The project needs 50 more work packages to be completed to be on time.
  4. There is not enough information
Correct Answer

Q6. All of the following are used in quality management EXCEPT:

  1. Marginal analysis
  2. Selected sellers
  3. Standard deviation
  4. The Delphi technique.
Correct Answer

Q7. A project manager is concerned about the amount of gold plating that has occurred on past projects. All the following would NOT be of use in controlling gold plating EXCEPT:

  1. A staffing management plan
  2. A project charter
  3. A work breakdown structure dictionary
  4. A risk management plan
Correct Answer

Q8. Senior management asks the project manager how the project would be affected if two resources were removed from the project. To calculate a response, the project manager should complete:

  1. Resource leveling
  2. What-if scenario analysis
  3. Schedule compression
  4. Fast tracking
Correct Answer

Q9. While preparing your risk responses, you identify additional risks. What should you do?

  1. Add reserves to the project to accommodate the new risks and notify management.
  2. Document the risk items and calculate the expected monetary value based on probability and impact that result from the occurrences.
  3. Determine the risk events and the associated cost, and then add the cost to the project budget as a reserve.
  4. Add a 10 percent contingency to the project budget and notify the customer.
Correct Answer

Q10. The buyer asks the project manager for the status of the project that his team is working on. What is the BEST way to determine the status of a project?

  1. Compare the project performance against the project baselines
  2. Compare the earned value to the planned value
  3. Compare the project performance against the integrated change control plan.
  4. Compare the number of people used on each work package to the planned number to be used.
Correct Answer










User Agreement| |Privacy Policy